Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 699.175 | 0 | 200 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 699.175 | 217 | 200 | 89.857 | 89.857 | 71.155 | 288.155 | 282.175 | 60% |
41% May - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-3
Package 2 KM 4-12
Package 3 KM 13-23
Package 4 Ancillary work | |||||||||||||||||||
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 91.357 | 91.357 | 17.988 | 234.988 | 0 | 100% |
100% December - 2020 |
Work in progress. |
No Image |
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 91.357 | 91.357 | 17.988 | 234.988 | 0 | 100% |
100% December - 2020 |
Work in progress. |
No Image |
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 200 | 60 | 0 | 217 | 0 | 100% |
100% October - 2020 |
Work in progress. |
No Image |
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 200 | 60 | 0 | 217 | 0 | 100% |
100% September - 2020 |
Work in progress. |
No Image |
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 200 | 60 | 0 | 217 | 0 | 100% |
100% August - 2020 |
Work in progress. |
No Image |
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 89.857 | 89.857 | 56.87 | 273.87 | 0 | 100% |
100% April - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-3
Package 2 KM 4-12
Package 3 KM 13-23
Package 4 Ancillary work | |||||||||||||||||||
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 129.857 | 129.857 | 18.03 | 235.03 | 0 | 100% |
100% March - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-3
Package 2 KM 4-12
Package 3 KM 13-23
Package 4 Ancillary work | |||||||||||||||||||
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 129.857 | 129.857 | 18.03 | 235.03 | 0 | 100% |
100% February - 2021 |
Work in progress. |
No Image |
Package 1 KM 1-3
Package 2 KM 4-12
Package 3 KM 13-23
Package 4 Ancillary work | |||||||||||||||||||
1905 (OG) |
195268-Improvement & Rehabilitation of Parachinar Tarimangal Road (23-KMs) (TR) (AIP) |
Kurram HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 199.175 | 217 | 200 | 129.857 | 129.857 | 18.03 | 235.03 | 0 | 100% |
100% January - 2021 |
Work in progress. |
No Image |