Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
30-11--1 30-11--1 - 30-11--1 - 46.031 0 20 0 0 0 0 0 -
July - 2020
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
30-11--1 30-11--1 - 30-11--1 - 46.031 26.88 20 11.636 11.636 0 26.88 0 100% 58%
May - 2021
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 36.3121 26.88 20 8.136 8.136 0 26.88 0 100% 74%
December - 2020
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 36.3121 26.88 20 8.136 8.136 0 26.88 0 100% 74%
December - 2020
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 46.031 26.88 20 20 5 0 26.88 0 100% 58%
October - 2020
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 46.031 26.88 20 20 5 0 26.88 0 100% 58%
September - 2020
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 46.031 26.88 20 20 5 0 26.88 0 100% 58%
August - 2020
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 36.3121 26.88 20 11.636 11.636 0 26.88 0 100% 74%
April - 2021
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 36.3121 26.88 20 11.636 11.636 0 26.88 0 100% 74%
March - 2021
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 36.3121 26.88 20 11.636 11.636 0 26.88 0 100% 74%
February - 2021
Earth Work & S/Work in progress.
No Image
1901
(OG)
195261-Construction of BT Road from Luqmankhail to Kas 2-KMs Kurram (FMR) (AIP)
Kurram
HW
30-11--1 30-11--1 - 30-11--1 - 36.3121 26.88 20 11.636 11.636 0 26.88 0 100% 74%
January - 2021
Earth Work & S/Work in progress.
No Image