Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 30 | 14.704 | 0 | 64.832 | 0 | 100% |
75% December - 2020 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress. |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 30 | 14.704 | 0 | 64.832 | 0 | 100% |
75% December - 2020 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress. |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 30 | 14.704 | 0 | 64.832 | 0 | 100% |
75% October - 2020 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress. |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 30 | 10 | 0 | 64.832 | 0 | 100% |
75% September - 2020 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress. |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 30 | 0 | 0 | 64.832 | 0 | 100% |
75% August - 2020 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress. |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 25.411 | 25.411 | 9.568 | 74.4 | 0 | 100% |
86% May - 2021 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress.
P-II Balance fund |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 25.411 | 25.411 | 9.568 | 74.4 | 0 | 100% |
86% April - 2021 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress.
P-II Balance fund |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 25.411 | 25.411 | 0 | 64.832 | 0 | 100% |
75% March - 2021 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress.
P-II Balance fund |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 25.411 | 25.411 | 0 | 64.832 | 0 | 100% |
75% February - 2021 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress.
P-II Balance fund |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 64.832 | 30 | 25.411 | 25.411 | 0 | 64.832 | 0 | 100% |
75% January - 2021 |
Length 4 km - EW 90 % , Sub base 80 % Structure in progress.
P-II Balance fund |
No Image |
1894 (OG) |
195252-Construction of Black Topped Road from Isha Razmak Road to Lakkay Asad Khel village,Phase-II Tehsil Razmak Sub Division Razmak (4 KM) balance portion (FMR) (AIP) |
North Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 86.296 | 0 | 30 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
Pages : 1 |