Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 242.587 0 15 15 32.993 15 15 227.587 6% 6%
October - 2020
Work in progress.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 242.587 0 15 15 15 15 15 227.587 6% 6%
September - 2020
Work in progress.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
North Waziristan
30-11--1 30-11--1 - 30-11--1 - 0 0 15 15 15 0 0 0 - -
August - 2020
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 198.877 0 76.662 76.662 76.662 0 0 122.215 39% -
December - 2020
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 198.877 0 76.662 76.662 76.662 0 0 122.215 39% -
December - 2020
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
October - 2020
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
September - 2020
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 198.877 0 76.662 76.662 76.662 0 0 122.215 39% -
March - 2021
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 198.877 0 76.662 76.662 76.662 0 0 122.215 39% -
February - 2021
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 198.877 0 76.662 76.662 76.662 0 0 122.215 39% -
January - 2021
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 198.877 0 76.662 76.662 76.662 0 0 122.215 39% -
May - 2021
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 198.877 0 76.662 76.662 76.662 0 0 122.215 39% -
April - 2021
Detail cost estimate submitted.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
December - 2020
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
December - 2020
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
October - 2020
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
September - 2020
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
August - 2020
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 0 0 0 122.215 0
July - 2020
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
May - 2021
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
April - 2021
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
March - 2021
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
February - 2021
Completion : June-2021.
No Image
1879
(OG)
191848-170337-Construction of Bridges in All Agencies, FATA [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 198.877 122.215 76.662 76.662 0 0 122.215 0 - -
January - 2021
Completion : June-2021.
No Image
Pages : 1