Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 395.353 0 5 5 21.429 5 5 390.353 1% 1%
October - 2020
E/work, Sub Base, B/C & S/Work in progress.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 395.353 0 5 5 5 5 5 390.353 1% 1%
September - 2020
E/work, Sub Base, B/C & S/Work in progress.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 5 0 99.5 225.853 43% 25%
August - 2020
03-Packages E/work, Sub Base, B/C & S/Work in progress.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 395.353 66 70 0 0 0 66 0
July - 2020
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 70 48.938 148.438 225.853 43% 38%
March - 2021
03 - Units all in progress
No Image
  1. Package 1 (KM 1 to 7)
  2. Package II (KM 8 to 14)
  3. Package III (KM 15 to 21)
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 70 48.938 148.438 225.853 43% 38%
February - 2021
03 - Units all in progress
No Image
  1. Package 1 (KM 1 to 7)
  2. Package II (KM 8 to 14)
  3. Package III (KM 15 to 21)
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 395.353 0 5 5 21.429 21.429 21.429 390.353 1% 5%
January - 2021
E/work, Sub Base, B/C & S/Work in progress.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 0 0 99.5 225.853 43% 25%
December - 2020
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 0 0 99.5 225.853 43% 25%
December - 2020
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 5 0 99.5 225.853 43% 25%
October - 2020
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 5 0 99.5 225.853 43% 25%
September - 2020
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 0 0 0 99.5 225.853 43% 25%
March - 2021
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 0 0 0 99.5 225.853 43% 25%
February - 2021
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 0 0 0 99.5 225.853 43% 25%
January - 2021
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 0 0 0 99.5 225.853 43% 25%
May - 2021
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Orakzai
HW
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 0 0 0 99.5 225.853 43% 25%
April - 2021
Share not yet identified.
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
December - 2020
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
December - 2020
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
October - 2020
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 0 0 5 0 0 395.353 - -
September - 2020
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
May - 2021
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
April - 2021
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
March - 2021
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
February - 2021
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 395.353 0 70 70 5 0 0 325.353 18% -
January - 2021
No Image
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Tank
HW
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 70 48.938 148.438 225.853 43% 38%
May - 2021
03 - Units all in progress
No Image
  1. Package 1 (KM 1 to 7)
  2. Package II (KM 8 to 14)
  3. Package III (KM 15 to 21)
1874
(OG)
191841-170399-Construction of Link Roads to CPEC in Tribal Districts. [MA]
Tank
HW
30-11--1 30-11--1 - 30-11--1 - 395.353 99.5 70 70 70 48.938 148.438 225.853 43% 38%
April - 2021
03 - Units all in progress
No Image
  1. Package 1 (KM 1 to 7)
  2. Package II (KM 8 to 14)
  3. Package III (KM 15 to 21)
Pages : 1