Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 0 0 0 89.28 0
July - 2020
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 3.378 92.658 0 100% 97%
October - 2020
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 1.4 90.68 0 100% 95%
September - 2020
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 0 89.28 0 100% 94%
August - 2020
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 4.25 93.53 0 100% 98%
December - 2020
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 4.25 93.53 0 100% 98%
December - 2020
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 6.104 95.384 0 100% 100%
May - 2021
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 6.104 95.384 0 100% 100%
April - 2021
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 6.104 95.384 0 100% 100%
March - 2021
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 6.104 95.384 0 100% 100%
February - 2021
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image
1871
(OG)
191835-150147-Design & Rehabilitation of Damaged Portions of Roads in SWA Phase-II, Gomal Zam WANA Road. (Km-66 to Km-117). [MA]
South Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 95.384 89.28 6.104 6.104 6.104 4.25 93.53 0 100% 98%
January - 2021
(Length 8Km) E/W , S/B ,B/C & S/Work in progress. Completion : June-2021.
No Image