Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 37.635 | 0 | 0 | 0 | 110.175 | 0.666 | 100% |
74% July - 2020 |
Work in progress. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 18.833 | 0.833 | 0.833 | 0 | 110.175 | 19.468 | 87% |
74% December - 2020 |
Consultancy Scheme.
F/S Completed
Funds Reappropriated |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 18.833 | 0.833 | 0.833 | 0 | 110.175 | 19.468 | 87% |
74% December - 2020 |
Consultancy Scheme.
F/S Completed
Funds Reappropriated |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 10 | 10 | 10 | 0 | 110.175 | 28.301 | 81% |
74% October - 2020 |
Work in progress. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 10 | 10 | 10 | 0 | 110.175 | 28.301 | 81% |
74% September - 2020 |
Work in progress. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 10 | 10 | 10 | 0 | 110.175 | 28.301 | 81% |
74% August - 2020 |
Work in progress. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 18.833 | 0.833 | 0.833 | 0 | 110.175 | 19.468 | 87% |
74% May - 2021 |
Consultancy Scheme.
F/S Completed
Funds Reappropriated |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 18.833 | 0.833 | 0.833 | 0 | 110.175 | 19.468 | 87% |
74% April - 2021 |
Consultancy Scheme.
F/S Completed
Funds Reappropriated |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 18.833 | 0.833 | 0.833 | 0 | 110.175 | 19.468 | 87% |
74% March - 2021 |
Consultancy Scheme.
F/S Completed
Funds Reappropriated |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 18.833 | 0.833 | 0.833 | 0 | 110.175 | 19.468 | 87% |
74% February - 2021 |
Consultancy Scheme.
F/S Completed
Funds Reappropriated |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Khyber HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.175 | 18.833 | 0.833 | 0.833 | 0 | 110.175 | 19.468 | 87% |
74% January - 2021 |
Consultancy Scheme.
F/S Completed
Funds Reappropriated |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 37.635 | 37.635 | 0 | 0 | 73.688 | 37.153 | 75% |
50% December - 2020 |
No Image | |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 37.635 | 37.635 | 0 | 0 | 73.688 | 37.153 | 75% |
50% December - 2020 |
No Image | |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 0 | 0 | 0 | 0 | 73.688 | 74.788 | - |
50% October - 2020 |
No Image | |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 0 | 0 | 0 | 0 | 73.688 | 74.788 | - |
50% September - 2020 |
No Image | |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 37.635 | 0 | 0 | 0 | 73.688 | 37.153 | 75% |
50% March - 2021 |
work started |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 37.635 | 0 | 0 | 0 | 73.688 | 37.153 | 75% |
50% February - 2021 |
work started |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 37.635 | 0 | 0 | 0 | 73.688 | 37.153 | 75% |
50% January - 2021 |
work started |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 37.635 | 0 | 0 | 0 | 73.688 | 37.153 | 75% |
50% May - 2021 |
work started |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 73.688 | 37.635 | 0 | 0 | 0 | 73.688 | 37.153 | 75% |
50% April - 2021 |
work started |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- October - 2020 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- September - 2020 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- August - 2020 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 0 | 0 | 0 | 110.841 | 0 |
July - 2020 |
No Image | ||
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- May - 2021 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- April - 2021 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- March - 2021 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- February - 2021 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 148.476 | 110.841 | 37.635 | 37.635 | 0 | 0 | 110.841 | 0 | - |
- January - 2021 |
Completion : June-2021. |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% December - 2020 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% December - 2020 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% October - 2020 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% September - 2020 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% August - 2020 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% May - 2021 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% April - 2021 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% March - 2021 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% February - 2021 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
1870 (OG) |
191834-070009-Feasibility and Design of Pre-stressed RCC Bridges, Roads and Buildings in FATA, (Phase-II) (Revised) [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 42.4 | 110.175 | 0 | 0 | 0 | 0 | 110.175 | 0 | - |
100% January - 2021 |
PC-II for contruction of RCC Bridge on Shahoor river sent to SE South C&W MA |
No Image |
Pages : 1 |