Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 20 | 20 | 20 | 79.694 | 20% |
20% May - 2021 |
Earth work in progress. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 20 | 20 | 20 | 79.694 | 20% |
20% April - 2021 |
Earth work in progress. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 9.694 | 9.694 | 9.694 | 79.694 | 20% |
10% December - 2020 |
Earth work in progress. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 9.694 | 9.694 | 9.694 | 79.694 | 20% |
10% December - 2020 |
Earth work in progress. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 5 | 3.617 | 3.617 | 79.694 | 20% |
4% October - 2020 |
Earth work in progress. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 5 | 0 | 0 | 79.694 | 20% |
- September - 2020 |
Layout given. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 0 | 0 | 0 | 79.694 | 20% |
- August - 2020 |
Layout given. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 20 | 20 | 20 | 79.694 | 20% |
20% March - 2021 |
Earth work in progress. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 20 | 20 | 20 | 79.694 | 20% |
20% February - 2021 |
Earth work in progress. |
No Image |
1856 (OG) |
200126-Construction of 4Kms BTR Shakir Kalay Area Darazanda Sub Division |
FR DI Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.694 | 0 | 20 | 20 | 20 | 17.303 | 17.303 | 79.694 | 20% |
17% January - 2021 |
Earth work in progress. |
No Image |
Pages : 1 |