Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 57.546 16.16 30.151 30.151 30.151 28.887 45.047 11.235 80% 78%
May - 2021
02- Units Work in progress. Cannot be complted due to local dispute.
No Image
  1. BTR from naraiya Soreyae to Tora Umer Zai 2 KM
  2. BT road form Ehsan UL Haq to Main Almar Kalan 2 KM
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 57.546 16.16 30.151 30.151 30.151 28.887 45.047 11.235 80% 78%
April - 2021
02- Units Work in progress. Cannot be complted due to local dispute.
No Image
  1. BTR from naraiya Soreyae to Tora Umer Zai 2 KM
  2. BT road form Ehsan UL Haq to Main Almar Kalan 2 KM
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 11.08 30 30 30 19.983 31.063 16.466 71% 54%
December - 2020
02- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 11.08 30 30 30 19.983 31.063 16.466 71% 54%
December - 2020
02- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 11.08 15 15 15 7.5 18.58 31.466 45% 32%
October - 2020
02- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 11.08 15 15 15 4.84 15.92 31.466 45% 28%
September - 2020
02- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 11.08 0 0 0 0 11.08 46.466 - 19%
August - 2020
02- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 98.714 34.16 64.554 0 0 0 34.16 0
July - 2020
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 16.16 30.151 30.151 30.151 28.887 45.047 11.235 80% 78%
March - 2021
02- Units Work in progress.
No Image
  1. BTR from naraiya Soreyae to Tora Umer Zai 2 KM
  2. BT road form Ehsan UL Haq to Main Almar Kalan 2 KM
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 16.16 30.151 30.151 30.151 28.887 45.047 11.235 80% 78%
February - 2021
02- Units Work in progress.
No Image
  1. BTR from naraiya Soreyae to Tora Umer Zai 2 KM
  2. BT road form Ehsan UL Haq to Main Almar Kalan 2 KM
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR DI Khan
30-11--1 30-11--1 - 30-11--1 - 57.546 11.08 30 30 30 24.605 35.685 16.466 71% 62%
January - 2021
02- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
December - 2020
03- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
December - 2020
03- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
October - 2020
03- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
September - 2020
03- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
August - 2020
03- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
March - 2021
03- Units Work in progress.
No Image
  1. BTR from village Bora Khel Remaining portion 1 KM
  2. Sobati Katch to Khirgi (Missing portion) 1 KM
  3. Raod form Asman Kali Gulistant kot to Pirtangi road 1 KM
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
February - 2021
03- Units Work in progress.
No Image
  1. BTR from village Bora Khel Remaining portion 1 KM
  2. Sobati Katch to Khirgi (Missing portion) 1 KM
  3. Raod form Asman Kali Gulistant kot to Pirtangi road 1 KM
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
FR Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
January - 2021
03- Units Work in progress.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
December - 2020
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
December - 2020
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
October - 2020
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
September - 2020
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
August - 2020
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
May - 2021
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
April - 2021
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
March - 2021
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
February - 2021
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 98.714 0 64.554 64.554 0 0 0 0 - -
January - 2021
Completion : June-2021.
No Image
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
May - 2021
03- Units 1. 2. 3. Asman Kali Gulistant Kot to Pirtangi Road Cannot be completed due to site dispute
No Image
  1. BTR from village Bora Khel Remaining portion 1 KM
  2. Sobati Katch to Khirgi (Missing portion) 1 KM
  3. Raod form Asman Kali Gulistant kot to Pirtangi road 1 KM
1855
(OG)
191828-190283 - Construction of Black Topped Roads in Tribal Sub-Divisions Jandola & Darazinda. [MA]
Tank
30-11--1 30-11--1 - 30-11--1 - 40.968 5.08 0 0 0 0 5.08 35.888 - 12%
April - 2021
03- Units 1. 2. 3. Asman Kali Gulistant Kot to Pirtangi Road Cannot be completed due to site dispute
No Image
  1. BTR from village Bora Khel Remaining portion 1 KM
  2. Sobati Katch to Khirgi (Missing portion) 1 KM
  3. Raod form Asman Kali Gulistant kot to Pirtangi road 1 KM
Pages : 1