Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 0 | 0 | 0 | 99.025 | 0 | 100% |
71% July - 2020 |
Work in Progress.
T.S submitted to SE North Tribal Circle Peshawar. |
No Image |
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 41.088 | 28.491 | 127.516 | 0 | 100% |
91% December - 2020 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 41.088 | 28.491 | 127.516 | 0 | 100% |
91% December - 2020 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 19.643 | 19.643 | 118.668 | 0 | 100% |
85% October - 2020 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 10 | 0 | 99.025 | 0 | 100% |
71% September - 2020 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 0 | 0 | 99.025 | 0 | 100% |
71% August - 2020 |
Work in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 41.088 | 41.088 | 140.113 | 0 | 100% |
100% May - 2021 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Can be complted provided balance funds of Rs. 10.99 m provided as per TS. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 41.088 | 41.088 | 140.113 | 0 | 100% |
100% April - 2021 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Can be complted provided balance funds of Rs. 10.99 m provided as per TS. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 41.088 | 34.449 | 133.474 | 0 | 100% |
95% March - 2021 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 41.088 | 34.449 | 133.474 | 0 | 100% |
95% February - 2021 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
1845 (OG) |
191792-180204 - Rehabilitation of Existing Black Topped roads in District Bajaur. [MA] |
Bajaur HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 140.113 | 99.025 | 41.088 | 41.088 | 41.088 | 28.491 | 127.516 | 0 | 100% |
91% January - 2021 |
03- Units
Road Work completed. S/Work & Premix in Progress.
T.S submitted to SE North Tribal Circle Peshawar.
Completion : June 2021. |
No Image |
1) Ghar Shamozai road 5-Km
2) Badan Mamund road 3 Km
3) Shahgo to Kharkai road (5-km)
| |||||||||||||||||||
Pages : 1 |