Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 0 0 0 216.979 0 100% 75%
July - 2020
7- Units 5- completed. 2 - In progress.
No Image
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 71.212 31.713 5.683 222.662 0 100% 77%
December - 2020
7- Units 5- completed. 1 - In progress. 1- unit -executed by Pak Army Completion : June 2021.
No Image
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 71.212 31.713 5.683 222.662 0 100% 77%
December - 2020
7- Units 5- completed. 1 - In progress. 1- unit -executed by Pak Army Completion : June 2021.
No Image
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 71.212 15 0 216.979 0 100% 75%
October - 2020
7- Units 5- completed. 2 - In progress. Completion : June 2021.
No Image
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 71.212 15 0 216.979 0 100% 75%
September - 2020
7- Units 5- completed. 2 - In progress. Completion : June 2021.
No Image
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 71.212 0 0 216.979 0 100% 75%
August - 2020
7- Units 5- completed. 2 - In progress. Completion : June 2021.
No Image
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 71.212 71.212 31.713 248.692 0 100% 86%
May - 2021
7- Units 5- completed. 1 - In progress. 1- unit -executed by Pak Army Can be complted provided balance allocation funds of Rs. 39.499 m provided.
No Image
  1. Rehab: of Hasham Charmang Road 4 KM
  2. Rehab: of Lara Khalozo to Mena Mamund road 3 KM
  3. Rehab: of Arang Main Road  4 KM .?.?. (TS 16.392)
  4. Rehab: of Inayat Killi Scout Fort to Shinkot 3 KM
  5. Rehab: of Shahgo to Landai road 6 KM form KM 1
  6. Rehab: of  Mena to Mukha road 2 KM .?.?. (TS 11.163)
  7. Operational Tracks for Pak Army in Bajaur
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 31.713 31.713 31.713 248.692 0 100% 86%
April - 2021
7- Units 5- completed. 1 - In progress. 1- unit -executed by Pak Army Can be complted provided balance allocation funds of Rs. 39.499 m provided.
No Image
  1. Rehab: of Hasham Charmang Road 4 KM
  2. Rehab: of Lara Khalozo to Mena Mamund road 3 KM
  3. Rehab: of Arang Main Road  4 KM .?.?. (TS 16.392)
  4. Rehab: of Inayat Killi Scout Fort to Shinkot 3 KM
  5. Rehab: of Shahgo to Landai road 6 KM form KM 1
  6. Rehab: of  Mena to Mukha road 2 KM .?.?. (TS 11.163)
  7. Operational Tracks for Pak Army in Bajaur
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 31.713 31.713 24.371 241.35 0 100% 84%
March - 2021
7- Units 5- completed. 1 - In progress. 1- unit -executed by Pak Army Completion : June 2021.
No Image
  1. Rehab: of Hasham Charmang Road 4 KM
  2. Rehab: of Lara Khalozo to Mena Mamund road 3 KM
  3. Rehab: of Arang Main Road  4 KM .?.?. (TS 16.392)
  4. Rehab: of Inayat Killi Scout Fort to Shinkot 3 KM
  5. Rehab: of Shahgo to Landai road 6 KM form KM 1
  6. Rehab: of  Mena to Mukha road 2 KM .?.?. (TS 11.163)
  7. Operational Tracks for Pak Army in Bajaur
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 31.713 31.713 24.371 241.35 0 100% 84%
February - 2021
7- Units 5- completed. 1 - In progress. 1- unit -executed by Pak Army Completion : June 2021.
No Image
  1. Rehab: of Hasham Charmang Road 4 KM
  2. Rehab: of Lara Khalozo to Mena Mamund road 3 KM
  3. Rehab: of Arang Main Road  4 KM .?.?. (TS 16.392)
  4. Rehab: of Inayat Killi Scout Fort to Shinkot 3 KM
  5. Rehab: of Shahgo to Landai road 6 KM form KM 1
  6. Rehab: of  Mena to Mukha road 2 KM .?.?. (TS 11.163)
  7. Operational Tracks for Pak Army in Bajaur
1843
(OG)
191749-170013-Maintenance & Rehabilitation of 22-kms Existing Black Topped roads in Bajaur Agency. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 288.191 216.979 71.212 31.713 31.713 5.683 222.662 0 100% 77%
January - 2021
7- Units 5- completed. 1 - In progress. 1- unit -executed by Pak Army Completion : June 2021.
No Image
Pages : 1