Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 0 0 0 81.784 281.221 28% 21%
July - 2020
4 - Units 1- Completed 3- In progress.
No Image
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 25 25 106.784 281.221 28% 28%
December - 2020
4 - Units 1- Completed 2- In progress. 3- Work resumed 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo. Demand Rs. 120 M
No Image
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 25 25 106.784 281.221 28% 28%
December - 2020
4 - Units 1- Completed 2- In progress. 3- Work resumed 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo. Demand Rs. 120 M
No Image
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 10.868 10.868 92.652 281.221 28% 24%
October - 2020
4 - Units 1- Completed 2- In progress. 3- Work stopped due to Law& order situation. 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo.
No Image
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 5 5 86.784 281.221 28% 22%
September - 2020
4 - Units 1- Completed 2- In progress. 3- Work stopped due to Law& order situation. 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo.
No Image
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 0 0 81.784 281.221 28% 21%
August - 2020
4 - Units 1- Completed 3 In progress.
No Image
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 50 50 50 131.784 281.221 28% 34%
May - 2021
4 - Units 1- Completed 2- In progress. 3- Work resumed 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo. Demand Rs. 50 M
No Image
  1. BT of Tofansha to Daman Salarzai 3 KM
  2. Cosnt: of BTR Chawgat to Bagandel road 4.8 KM
  3. Const: of BTR Sharif Khana to Niag Banda via Tangai and Garigal 8 KM
  4. Const: of BTR road connection form Landai Wara Mamund to Mena Loe-Mamund 2 KM
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 25 25 106.784 281.221 28% 28%
April - 2021
4 - Units 1- Completed 2- In progress. 3- Work resumed 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo. Demand Rs. 50 M
No Image
  1. BT of Tofansha to Daman Salarzai 3 KM
  2. Cosnt: of BTR Chawgat to Bagandel road 4.8 KM
  3. Const: of BTR Sharif Khana to Niag Banda via Tangai and Garigal 8 KM
  4. Const: of BTR road connection form Landai Wara Mamund to Mena Loe-Mamund 2 KM
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 25 25 106.784 281.221 28% 28%
March - 2021
4 - Units 1- Completed 2- In progress. 3- Work resumed 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo. Demand Rs. 120 M
No Image
  1. BT of Tofansha to Daman Salarzai 3 KM
  2. Cosnt: of BTR Chawgat to Bagandel road 4.8 KM
  3. Const: of BTR Sharif Khana to Niag Banda via Tangai and Garigal 8 KM
  4. Const: of BTR road connection form Landai Wara Mamund to Mena Loe-Mamund 2 KM
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 25 25 106.784 281.221 28% 28%
February - 2021
4 - Units 1- Completed 2- In progress. 3- Work resumed 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo. Demand Rs. 120 M
No Image
  1. BT of Tofansha to Daman Salarzai 3 KM
  2. Cosnt: of BTR Chawgat to Bagandel road 4.8 KM
  3. Const: of BTR Sharif Khana to Niag Banda via Tangai and Garigal 8 KM
  4. Const: of BTR road connection form Landai Wara Mamund to Mena Loe-Mamund 2 KM
1842
(OG)
191748-170012-Construction and Black Topping of 17.8-Kms Roads in District Bajaur. [MA]
Bajaur
HW
30-11--1 30-11--1 - 30-11--1 - 388.005 81.784 25 25 25 25 106.784 281.221 28% 28%
January - 2021
4 - Units 1- Completed 2- In progress. 3- Work resumed 4- Work in progress on Km-1.4. The scheme has been subjudice. Court has been approached for early vacation of status quo. Demand Rs. 120 M
No Image