Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 49.003 | 23.501 | 21.821 | 171.542 | 0 | 100% |
86% December - 2020 |
(Length=13.5 Km)
06- components
work in progress.
Completion : June-2021. |
No Image |
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 49.003 | 23.501 | 21.821 | 171.542 | 0 | 100% |
86% December - 2020 |
(Length=13.5 Km)
06- components
work in progress.
Completion : June-2021. |
No Image |
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 49.003 | 12 | 9.145 | 158.866 | 0 | 100% |
80% October - 2020 |
(Length=13.5 Km)
06- components
work in progress.
Completion : June-2021. |
No Image |
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 49.003 | 12 | 9.145 | 158.866 | 0 | 100% |
80% September - 2020 |
(Length=13.5 Km)
06- components
work in progress.
Completion : June-2021. |
No Image |
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 49.003 | 12 | 0 | 149.721 | 0 | 100% |
75% August - 2020 |
06- components
work in progress.
Completion : June-2021. |
No Image |
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 0 | 0 | 0 | 149.721 | 0 |
July - 2020 |
No Image | ||
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 23.501 | 23.501 | 21.821 | 171.542 | 0 | 100% |
86% March - 2021 |
(Length=13.5 Km)
06- components
work in progress.
Completion : June-2021. |
No Image |
| |||||||||||||||||||
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 23.501 | 23.501 | 21.821 | 171.542 | 0 | 100% |
86% February - 2021 |
(Length=13.5 Km)
06- components
work in progress.
Completion : June-2021. |
No Image |
| |||||||||||||||||||
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 23.501 | 23.501 | 21.821 | 171.542 | 0 | 100% |
86% January - 2021 |
(Length=13.5 Km)
06- components
work in progress.
Completion : June-2021. |
No Image |
13.5 KM road Mohmand Agency | |||||||||||||||||||
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 22.651 | 22.651 | 21.821 | 171.542 | 0 | 100% |
86% May - 2021 |
(Length=13.5 Km)
Delete . Drop from ADP |
No Image |
| |||||||||||||||||||
1836 (OG) |
191754-170045-Construction of 13.5 Kms Black Topped Link Roads in Different Areas in Mohmand Agency. [MA] |
Mohmand HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 198.724 | 149.721 | 49.003 | 23.501 | 23.501 | 21.821 | 171.542 | 0 | 100% |
86% April - 2021 |
(Length=13.5 Km)
Delete . Drop from ADP |
No Image |
| |||||||||||||||||||