Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 184.679 | 20 | 20 | 9.694 | 2.221 | 186.9 | 75.682 | 73% |
67% December - 2020 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 184.679 | 20 | 20 | 9.694 | 2.221 | 186.9 | 75.682 | 73% |
67% December - 2020 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 184.679 | 20 | 20 | 5 | 2.157 | 186.836 | 75.682 | 73% |
67% October - 2020 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 184.679 | 20 | 20 | 5 | 0 | 184.679 | 75.682 | 73% |
66% September - 2020 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 184.679 | 20 | 20 | 5 | 0 | 184.679 | 75.682 | 73% |
66% August - 2020 |
work in progress. |
No Image |
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 184.679 | 20 | 0 | 0 | 0 | 184.679 | 0 |
July - 2020 |
No Image | ||
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 190.054 | 20 | 9.694 | 9.694 | 3.409 | 193.463 | 70.307 | 75% |
69% March - 2021 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1 2.5 KM B/T road form Kamali Halimzai to Tamanzai
2 2-Km B/T road from Main Pandiali road to Village Gardai Pandiali
3 2-KM B/T road from Main Ghallanai road to Mullayan Kamali Halimzai
4 -KM B/T road from Main Ambar road soor dagi to Kharai Darra Banaras Killi Ambar
5 2-KM Ghallani by pass road
6 4-KM B/T from Ghaiba Khwar to Sangar via Remi Khel Halizai. | |||||||||||||||||||
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 190.054 | 20 | 9.694 | 9.694 | 3.409 | 193.463 | 70.307 | 75% |
69% February - 2021 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1 2.5 KM B/T road form Kamali Halimzai to Tamanzai
2 2-Km B/T road from Main Pandiali road to Village Gardai Pandiali
3 2-KM B/T road from Main Ghallanai road to Mullayan Kamali Halimzai
4 -KM B/T road from Main Ambar road soor dagi to Kharai Darra Banaras Killi Ambar
5 2-KM Ghallani by pass road
6 4-KM B/T from Ghaiba Khwar to Sangar via Remi Khel Halizai. | |||||||||||||||||||
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 184.679 | 20 | 9.694 | 9.694 | 2.221 | 186.9 | 75.682 | 73% |
67% January - 2021 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1 2.5 KM B/T road form Kamali Halimzai to Tamanzai
2 2-Km B/T road from Main Pandiali road to Village Gardai Pandiali
3 2-KM B/T road from Main Ghallanai road to Mullayan Kamali Halimzai
4 -KM B/T road from Main Ambar road soor dagi to Kharai Darra Banaras Killi Ambar
5 2-KM Ghallani by pass road
6 4-KM B/T from Ghaiba Khwar to Sangar via Remi Khel Halizai. | |||||||||||||||||||
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 190.054 | 20 | 20 | 20 | 3.409 | 193.463 | 70.307 | 75% |
69% May - 2021 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1 2.5 KM B/T road form Kamali Halimzai to Tamanzai
2 2-Km B/T road from Main Pandiali road to Village Gardai Pandiali
3 2-KM B/T road from Main Ghallanai road to Mullayan Kamali Halimzai
4 -KM B/T road from Main Ambar road soor dagi to Kharai Darra Banaras Killi Ambar
5 2-KM Ghallani by pass road
6 4-KM B/T from Ghaiba Khwar to Sangar via Remi Khel Halizai. | |||||||||||||||||||
1835 (OG) |
191753-150048-Construction of Black Topped/Link Roads in various Areas of Mohmand Agency (Revised). [MA] |
Mohmand HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 280.361 | 190.054 | 20 | 9.694 | 9.694 | 3.409 | 193.463 | 70.307 | 75% |
69% April - 2021 |
(Length=14 Km)
6-Units
10-Km completed & 4 work in progress. |
No Image |
1 2.5 KM B/T road form Kamali Halimzai to Tamanzai
2 2-Km B/T road from Main Pandiali road to Village Gardai Pandiali
3 2-KM B/T road from Main Ghallanai road to Mullayan Kamali Halimzai
4 -KM B/T road from Main Ambar road soor dagi to Kharai Darra Banaras Killi Ambar
5 2-KM Ghallani by pass road
6 4-KM B/T from Ghaiba Khwar to Sangar via Remi Khel Halizai. | |||||||||||||||||||