Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2019, January - 2020, February - 2021, February - 2019, February - 2020, March - 2021, March - 2019, March - 2020, April - 2021, April - 2019, April - 2020, May - 2021, May - 2020, July - 2018, July - 2020, August - 2019, August - 2020, September - 2018, September - 2019, September - 2020, October - 2019, October - 2020, November - 2018, November - 2019, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 16.03 16.03 0 0 0 0 16.03 0 - 100%
September - 2018
Work order issued (1 unit).
No Image
1) GGHS Birot PK-45
2) GGHS Bakot
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 16.03 16.03 0 0 0 0 16.03 0 - 100%
July - 2018
Work order issued (1 unit).
No Image
1) GGHS Birot PK-45
2) GGHS Bakot
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
December - 2020
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
December - 2020
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
October - 2020
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Bannu
30-11--1 30-11--1 - 30-11--1 - 5.818 1.508 0 0 0 0 1.508 4.31 - 26%
September - 2018
Completed.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
September - 2020
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
August - 2020
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Bannu
30-11--1 30-11--1 - 30-11--1 - 5.818 1.508 0 0 0 0 1.508 4.31 - 26%
July - 2018
Completed.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
July - 2020
Work order issued on 16/03/2018. Mutation of land/
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
May - 2021
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Scope of work:
  • Main Building
  • B/Wall
  • Tube Well
  • Sub Offices
  • Chowkidar/Gurads Room
  • Water supply
  • Elec: Work
  • External Elec:
  • Over Head Tank 10000 Gallon
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
April - 2021
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
March - 2021
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
February - 2021
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 10.076 0 0 0 0 10.076 126.376 - 7%
January - 2021
Tehsil Bakka Khel _ site Disputed Sub Tehsil Sardi Khel - In progress.
No Image
Bannu
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
December - 2020
Work order issued. Land not yet identified (20-22 Kanal)
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
December - 2020
Work order issued. Land not yet identified (20-22 Kanal)
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
October - 2020
Work order issued. Land not yet identified (20-22 Kanal)
No Image
Construction of Tehsil Building Shabqaddar PK
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
September - 2020
Work order issued. Land not yet identified (20-22 Kanal)
No Image
Construction of Tehsil Building Shabqaddar PK
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
August - 2020
Work order issued. Land not yet identified.
No Image
Construction of Tehsil Building Shabqaddar PK
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
July - 2020
Work order issued. Land not yet identified.
No Image
Construction of Tehsil Building Shabqaddar PK
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
May - 2021
Rs: 20 M approved for Land acquisation Section -IV issued
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
April - 2021
Rs: 20 M approved for Land acquisation Section -IV issued
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
March - 2021
Rs: 20 M approved for Land acquisation Section -IV issued
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
February - 2021
Rs: 20 M approved for Land acquisation Section -IV issued
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
January - 2021
Rs: 20 M approved for Land acquisation Section -IV under process
No Image
Construction of Tehsil Building Shabqaddar PK-60
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Chitral
30-11--1 30-11--1 - 30-11--1 - 1.19 0 0 0 0 0 0 1.19 - -
September - 2018
Physically completed, contractor liabilities yet to be paid.
No Image
Chitral
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Chitral
30-11--1 30-11--1 - 30-11--1 - 1.19 0 0 0 0 0 0 1.19 - -
July - 2018
Physically completed, contractor liabilities yet to be paid.
No Image
Chitral
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 12.616 10.301 0 0 0 0 10.301 2.315 - 82%
September - 2018
Completed & H/O (2 units).
No Image
1) GMPS Wanda Kokar shifted to GMPS Basti Lal Kat PK-65
2) GPS Basti Mahir shifted to GPS Adda Himat PK-64
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 12.616 10.301 0 0 0 0 10.301 2.315 - 82%
July - 2018
Completed & H/O (2 units).
No Image
1) GMPS Wanda Kokar shifted to GMPS Basti Lal Kat PK-65
2) GPS Basti Mahir shifted to GPS Adda Himat PK-64
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 39.707 36.002 0 0 0 0 36.002 3.705 - 91%
September - 2018
Completed & H/O (3 units).
No Image
1) Cluster Hostel in Dir Lower--- Rs.18 m
2) GGHS Lajbook PK-96 --- Rs.12.914 m
3) GGHS Moranai PK-96
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 39.707 36.002 0 0 0 0 36.002 3.705 - 91%
July - 2018
Completed & H/O (3 units).
No Image
1) Cluster Hostel in Dir Lower--- Rs.18 m
2) GGHS Lajbook PK-96 --- Rs.12.914 m
3) GGHS Moranai PK-96
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Hangu
30-11--1 30-11--1 - 30-11--1 - 8.972 11.673 0 0 0 0 11.673 0 - 100%
September - 2018
Out of 3 units, 2 completed, 1 site dispute (GGMS Doaba).
No Image
1) GMS Shamal Din Karbogha PK-43
2) GGPS Sial Talab
3) GGMS Doaba
183
(OG)
140204-Continuation of ongoing ADP schemes for completion in 2014-15.
Hangu
30-11--1 30-11--1 - 30-11--1 - 8.972 11.673 0 0 0 0 11.673 0 - 100%
July - 2018
Out of 3 units, 2 completed, 1 site dispute (GGMS Doaba).
No Image
1) GMS Shamal Din Karbogha PK-43
2) GGPS Sial Talab
3) GGMS Doaba
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 0 0 0 0 35.5 54.946 - 39%
December - 2020
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 0 0 0 0 35.5 54.946 - 39%
December - 2020
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 0 0 0 0 0 0 90.446 - -
October - 2020
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 0 0 0 0 0 0 90.446 - -
September - 2020
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 0 0 0 0 0 0 90.446 - -
August - 2020
GF/FF SS in progress. Demand 20 m for tempo
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 0 0 0 0 0 0 90.446 - -
July - 2020
GF/FF SS in progress. Demand 20 m for tempo
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 2.5 2.5 2.5 2.5 38 52.446 42% 42%
May - 2021
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 2.5 2.5 2.5 2.5 38 52.446 42% 42%
April - 2021
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 2.5 2.5 2.5 2.5 38 52.446 42% 42%
March - 2021
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 2.5 2.5 2.5 2.5 38 52.446 42% 42%
February - 2021
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 35.5 0 0 0 0 35.5 54.946 - 39%
January - 2021
GF/FF SS in progress. Demand 20 m for tempo of Work
No Image
Haripur
183
(OG)
110441-Establishment of Cadet College in Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 777.245 50 141.496 141.496 123.624 123.624 173.624 585.749 25% 22%
December - 2018
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress.
No Image
Cadet College Lakki Marwat
183
(OG)
110441-Establishment of Cadet College in Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 777.245 50 141.496 141.496 100.748 99.848 149.848 585.749 25% 19%
November - 2018
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress.
No Image
Cadet College Lakki Marwat
183
(OG)
110441-Establishment of Cadet College in Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 777.245 50 141.496 141.496 100.748 99.848 149.848 585.749 25% 19%
November - 2018
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress.
No Image
Cadet College Lakki Marwat
183
(OG)
110441-Establishment of Cadet College in Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 777.245 50 141.496 190.974 190.974 190.974 240.974 585.749 25% 31%
April - 2019
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress.
No Image
Cadet College Lakki Marwat
183
(OG)
110441-Establishment of Cadet College in Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 777.245 50 141.496 186.496 186.496 186.496 236.496 585.749 25% 30%
March - 2019
LOA issued to consultant. Survey completed by consultant. BW, foundation in progress.
No Image
Cadet College Lakki Marwat
Pages : 1 2