Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 22.774 | 22.774 | 8.109 | 50.859 | 0 | 100% |
83% December - 2020 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 22.774 | 22.774 | 8.109 | 50.859 | 0 | 100% |
83% December - 2020 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 18.75 | 8 | 0 | 42.75 | 0 | 100% |
70% October - 2020 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 18.75 | 8 | 0 | 42.75 | 0 | 100% |
70% September - 2020 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 18.75 | 8 | 0 | 42.75 | 0 | 100% |
70% August - 2020 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 0 | 0 | 0 | 42.75 | 0 |
July - 2020 |
No Image | ||
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 12.401 | 12.401 | 1.55 | 44.3 | 0 | 100% |
72% March - 2021 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
Ghiljo Orakzai | |||||||||||||||||||
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 12.401 | 12.401 | 1.55 | 44.3 | 0 | 100% |
72% February - 2021 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
Ghiljo Orakzai | |||||||||||||||||||
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 12.401 | 12.401 | 1.34 | 44.09 | 0 | 100% |
72% January - 2021 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
Ghiljo Orakzai | |||||||||||||||||||
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 1.55 | 1.55 | 1.55 | 44.3 | 0 | 100% |
72% May - 2021 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
Ghiljo Orakzai | |||||||||||||||||||
1816 (OG) |
191710-170141-Construction & Black Topping of Ghuzgharh Road Phase-II in Orakzai Agency. [MA] |
Orakzai HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 61.5 | 42.75 | 18.75 | 12.401 | 12.401 | 1.55 | 44.3 | 0 | 100% |
72% April - 2021 |
S/B, B/C, S/W & Asphalt premix in progress.
Completion : June-2021. |
No Image |
Ghiljo Orakzai | |||||||||||||||||||