Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 69.81 31.384 31.384 61.384 0 100% 62%
December - 2020
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 69.81 31.384 31.384 61.384 0 100% 62%
December - 2020
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 69.81 31.384 8.498 38.498 0 100% 39%
October - 2020
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 69.81 15 0 30 0 100% 30%
September - 2020
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 69.81 15 0 30 0 - -
August - 2020
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 69.81 69.81 42.449 72.449 0 100% 73%
May - 2021
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 31.384 31.384 31.384 61.384 0 100% 62%
April - 2021
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 31.384 31.384 31.384 61.384 0 100% 62%
March - 2021
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 31.384 31.384 31.384 61.384 0 100% 62%
February - 2021
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Waziristan
HW
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 31.384 31.384 31.384 61.384 0 100% 62%
January - 2021
(Length 7-Km) E/Work, S/B, B/C & Structure work in progress. Completion : June-2021.
No Image
1806
(OG)
191801-180338 - Rehabilitation and Re-Construction of Existing roads in District North Waziristan. [MA]
North Wazirstan
30-11--1 30-11--1 - 30-11--1 - 99.81 30 69.81 0 0 0 30 0
July - 2020