Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 40 | 16.388 | 16.372 | 86.872 | 343.304 | 24% |
19% December - 2020 |
04- Components
E/W, S/B,B/C S/W in progress on 11 Km B/T road Patwela Tehsil Ladha and remaing 3 components E/Work in progress. |
No Image |
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 40 | 16.388 | 16.372 | 86.872 | 343.304 | 24% |
19% December - 2020 |
04- Components
E/W, S/B,B/C S/W in progress on 11 Km B/T road Patwela Tehsil Ladha and remaing 3 components E/Work in progress. |
No Image |
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 40 | 16.388 | 7 | 77.5 | 343.304 | 24% |
17% October - 2020 |
04- Components
E/W, S/B,B/C S/W in progress on 11 Km B/T road Patwela Tehsil Ladha and remaing 3 components E/Work in progress. |
No Image |
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 40 | 7 | 7 | 77.5 | 343.304 | 24% |
17% September - 2020 |
04- Components
E/W, S/B,B/C S/W in progress on 11 Km B/T road Patwela Tehsil Ladha and remaing 3 components E/Work in progress. |
No Image |
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 40 | 7 | 7 | 77.5 | 343.304 | 24% |
17% August - 2020 |
04- Components
Work in progress. |
No Image |
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 122.596 | 122.596 | 122.583 | 193.083 | 343.304 | 24% |
43% May - 2021 |
04- Components
All in progress |
No Image |
| |||||||||||||||||||
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 60 | 60 | 60 | 130.5 | 343.304 | 24% |
29% April - 2021 |
04- Components
All in progress |
No Image |
| |||||||||||||||||||
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 60 | 60 | 60 | 130.5 | 343.304 | 24% |
29% March - 2021 |
04- Components
All in progress |
No Image |
| |||||||||||||||||||
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 60 | 60 | 60 | 130.5 | 343.304 | 24% |
29% February - 2021 |
04- Components
All in progress |
No Image |
| |||||||||||||||||||
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 60 | 60 | 60 | 130.5 | 343.304 | 24% |
29% January - 2021 |
04- Components
E/W, S/B,B/C S/W in progress on 11 Km B/T road Patwela Tehsil Ladha and remaing 3 components E/Work in progress. |
No Image |
1791 (OG) |
191779-140334-Black Topping of Roads in District South Waziristan, Phase II (25 Kms). (Umbrella). [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 453.804 | 70.5 | 40 | 0 | 0 | 0 | 70.5 | 0 |
July - 2020 |
No Image | ||
Pages : 1 |