Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 48.977 | 21.495 | 4.285 | 139.744 | 0 | 100% |
76% December - 2020 |
04- Components
Length = 11.5 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 48.977 | 21.495 | 4.285 | 139.744 | 0 | 100% |
76% December - 2020 |
04- Components
Length = 11.5 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 48.977 | 21.495 | 4.285 | 139.744 | 0 | 100% |
76% October - 2020 |
04- Components
Length = 11.5 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 48.977 | 10 | 2.911 | 138.37 | 0 | 100% |
75% September - 2020 |
04- Components
Length = 11.5 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 48.977 | 10 | 0 | 135.459 | 0 | 100% |
73% August - 2020 |
04- Components
Length = 11.5 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 36.495 | 36.495 | 18.158 | 153.617 | 0 | 100% |
83% May - 2021 |
04- units all in progress |
No Image |
| |||||||||||||||||||
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 21.495 | 21.495 | 15.193 | 150.652 | 0 | 100% |
82% April - 2021 |
04- units all in progress |
No Image |
| |||||||||||||||||||
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 21.495 | 21.495 | 5.846 | 141.305 | 0 | 100% |
77% March - 2021 |
04- units all in progress |
No Image |
| |||||||||||||||||||
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 21.495 | 21.495 | 5.846 | 141.305 | 0 | 100% |
77% February - 2021 |
04- units all in progress |
No Image |
| |||||||||||||||||||
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Waziristan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.346 | 135.459 | 48.977 | 21.495 | 21.495 | 4.285 | 139.744 | 0 | 100% |
76% January - 2021 |
04- Components
Length = 11.5 Km
E/W, S/B,B/C & Structure work in progress.
Completion : June-2021. |
No Image |
1784 (OG) |
191764-170302-Construction of BT Road in Ladha Sub Division, SWA. [MA] |
South Wazirstan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.436 | 135.459 | 48.977 | 0 | 0 | 0 | 135.459 | 0 |
July - 2020 |
No Image | ||