Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 24.5 0 173.151 2.349 99% 87%
December - 2020
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 24.5 0 173.151 2.349 99% 87%
December - 2020
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 18.375 0 173.151 2.349 99% 87%
October - 2020
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 175.5 24.5 24.5 12.25 0 175.5 0 100% 88%
September - 2020
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 175.5 24.5 24.5 12.25 0 175.5 0 100% 88%
August - 2020
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 175.5 24.5 0 12.25 0 175.5 0 100% 88%
July - 2020
Length 13 Km - earth work completed.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 24.5 0 173.151 2.349 99% 87%
May - 2021
Length 13 Km - earth work completed. Cannot be Completed. Contractor Served Notice for resind.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 24.5 0 173.151 2.349 99% 87%
April - 2021
Length 13 Km - earth work completed. Cannot be Completed. Contractor Served Notice for resind.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 24.5 0 173.151 2.349 99% 87%
March - 2021
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 24.5 0 173.151 2.349 99% 87%
February - 2021
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
1630
(OG)
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 173.151 24.5 24.5 24.5 0 173.151 2.349 99% 87%
January - 2021
Length 13 Km - earth work completed. Completion : June 2021.
No Image
PK-93, Dir Upper (13 Km)
Pages : 1