Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 24.5 | 0 | 173.151 | 2.349 | 99% |
87% December - 2020 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 24.5 | 0 | 173.151 | 2.349 | 99% |
87% December - 2020 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 18.375 | 0 | 173.151 | 2.349 | 99% |
87% October - 2020 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 175.5 | 24.5 | 24.5 | 12.25 | 0 | 175.5 | 0 | 100% |
88% September - 2020 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 175.5 | 24.5 | 24.5 | 12.25 | 0 | 175.5 | 0 | 100% |
88% August - 2020 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 175.5 | 24.5 | 0 | 12.25 | 0 | 175.5 | 0 | 100% |
88% July - 2020 |
Length 13 Km - earth work completed. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 24.5 | 0 | 173.151 | 2.349 | 99% |
87% May - 2021 |
Length 13 Km - earth work completed.
Cannot be Completed.
Contractor Served Notice for resind. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 24.5 | 0 | 173.151 | 2.349 | 99% |
87% April - 2021 |
Length 13 Km - earth work completed.
Cannot be Completed.
Contractor Served Notice for resind. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 24.5 | 0 | 173.151 | 2.349 | 99% |
87% March - 2021 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 24.5 | 0 | 173.151 | 2.349 | 99% |
87% February - 2021 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
1630 (OG) |
151076- Construction of Nehag Dara Road (Phase-II) District Dir Upper. |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 173.151 | 24.5 | 24.5 | 24.5 | 0 | 173.151 | 2.349 | 99% |
87% January - 2021 |
Length 13 Km - earth work completed.
Completion : June 2021. |
No Image |
PK-93, Dir Upper (13 Km) | |||||||||||||||||||
Pages : 1 |