Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 100 42.307 285.554 37.609 90% 75%
December - 2020
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 100 42.307 285.554 37.609 90% 75%
December - 2020
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 25 25 268.247 37.609 90% 70%
October - 2020
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 25 25 268.247 37.609 90% 70%
September - 2020
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 25 0 243.247 37.609 90% 64%
August - 2020
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 0 25 0 243.247 37.609 90% 64%
July - 2020
Length 27 Km - cutting of 27 Km completed, WBM of
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 100 61.467 304.714 37.609 90% 80%
May - 2021
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 100 61.467 304.714 37.609 90% 80%
April - 2021
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 100 61.467 304.714 37.609 90% 80%
March - 2021
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 100 61.467 304.714 37.609 90% 80%
February - 2021
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1624
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road, (Phase-I) (27 km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 243.247 100 100 100 42.307 285.554 37.609 90% 75%
January - 2021
Length 27 Km - cutting of 27 Km completed, WBM in progress.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
Pages : 1