Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 50 37.5 62.5 373.952 17% 14%
December - 2020
E/Work 85 % completed S/Work 35% completed.
No Image
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 50 37.5 62.5 373.952 17% 14%
December - 2020
E/Work 85 % completed S/Work 35% completed.
No Image
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 37.5 8.333 33.333 373.952 17% 7%
October - 2020
E/Work 85 % completed S/Work 35% completed.
No Image
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 8.333 8.333 33.333 373.952 17% 7%
September - 2020
Work started.
No Image
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 8.333 8.333 33.333 373.952 17% 7%
August - 2020
Work started.
No Image
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 0 8.333 0 25 373.952 17% 6%
July - 2020
Work started.
No Image
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 50 50 75 373.952 17% 17%
March - 2021
E/Work 85 % completed S/Work 35% completed.
No Image
Package 1
Package 2
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 50 50 75 373.952 17% 17%
February - 2021
E/Work 85 % completed S/Work 35% completed.
No Image
Package 1
Package 2
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 50 50 50 75 373.952 17% 17%
January - 2021
E/Work 85 % completed S/Work 35% completed.
No Image
Package 1
Package 2
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 79 79 79 104 373.952 17% 23%
May - 2021
02 Units (6 KM) all in progresss E/Work 85 % completed S/Work 35% completed. Demand Rs: 165 M Cost of land to be paid 160.770 M
No Image
Package 1
Package 2
1620
(OG)
190450-Construction of Chakdarra Bypass Road (6 Km), Dir Lower
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 448.952 25 50 79 79 79 104 373.952 17% 23%
April - 2021
02 Units (6 KM) all in progresss E/Work 85 % completed S/Work 35% completed. Demand Rs: 165 M Cost of land to be paid 160.770 M
No Image
Package 1
Package 2
Pages : 1