Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 10 | 7.5 | 90.46001 | 77.04 | 55% |
53% December - 2020 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 10 | 7.5 | 90.46001 | 77.04 | 55% |
53% December - 2020 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 7.5 | 7.5 | 90.46001 | 77.04 | 55% |
53% October - 2020 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 2.5 | 2.5 | 85.46001 | 77.04 | 55% |
50% September - 2020 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 2.5 | 2.5 | 85.46001 | 77.04 | 55% |
50% August - 2020 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 0 | 2.5 | 0 | 82.96001 | 77.04 | 55% |
49% July - 2020 |
Length 110 mtr - piling completed, pile caping com |
No Image |
1) Construction of RCC Bridges at approach ro | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 10 | 10 | 92.96001 | 77.04 | 55% |
55% March - 2021 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 10 | 10 | 92.96001 | 77.04 | 55% |
55% February - 2021 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 10 | 10 | 92.96001 | 77.04 | 55% |
55% January - 2021 |
Length 110 mtr - piling completed, pile caping completed. |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 10 | 10 | 92.96001 | 77.04 | 55% |
55% May - 2021 |
02 Units
Strcture work completed approches in progress
Length 110 mtr - piling completed, pile caping completed.
Demand Rs: 15 M |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
1617 (OG) |
150966-Construciton of RCC Bridges at approach road Matako Rahim Abad, Shukarta Mayar Bridge, Dir Lower. |
Dir Lower HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 170 | 82.96001 | 10 | 10 | 10 | 10 | 92.96001 | 77.04 | 55% |
55% April - 2021 |
02 Units
Strcture work completed approches in progress
Length 110 mtr - piling completed, pile caping completed.
Demand Rs: 15 M |
No Image |
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr) | |||||||||||||||||||
Pages : 1 |