Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 4.243 | 14.737 | 12.736 | 54% |
54% December - 2019 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 4.243 | 14.737 | 12.736 | 54% |
54% November - 2019 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 4.243 | 14.737 | 12.736 | 54% |
54% October - 2019 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 0 | 10.494 | 12.736 | 54% |
38% September - 2019 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 0 | 0 | 0 | 0 | 10.494 | 16.979 | - |
38% August - 2019 |
work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 16.973 | 16.973 | 16.973 | 15.287 | 25.781 | 0.006 | 100% |
94% May - 2020 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 4.243 | 14.737 | 12.736 | 54% |
54% April - 2020 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 4.243 | 14.737 | 12.736 | 54% |
54% March - 2020 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 4.243 | 14.737 | 12.736 | 54% |
54% February - 2020 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms |
Peshawar BD-1 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.494 | 4.243 | 4.243 | 4.243 | 4.243 | 14.737 | 12.736 | 54% |
54% January - 2020 |
Work in progress. |
No Image |
Construction of 3 training rooms in PITE PK-10 Peshawar | |||||||||||||||||||
161 (OG) |
150147-Establishment of Model Secondary School Ring Road, Charsadda Road Portion, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 261 | 66.5665 | 0.001 | 0.001 | 0 | 0 | 66.5665 | 194.433 | 26% |
26% September - 2018 |
Land payment made. Site not H/O. |
No Image |
PK-01, Peshawar | |||||||||||||||||||
161 (OG) |
150147-Establishment of Model Secondary School Ring Road, Charsadda Road Portion, Peshawar. |
Peshawar BD-2 |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 261 | 66.5665 | 0.001 | 0.001 | 0 | 0 | 66.5665 | 194.433 | 26% |
26% July - 2018 |
Land payment made. Site not H/O. |
No Image |
PK-01, Peshawar | |||||||||||||||||||
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- December - 2019 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- November - 2019 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- October - 2019 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- September - 2019 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- August - 2019 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2020 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- May - 2020 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- April - 2020 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- March - 2020 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- February - 2020 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
161 (OG) |
170210-Upgradation of PITE Training Rooms. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 27.473 | 10.5 | 16.973 | 16.973 | 0 | 0 | 10.5 | 0 | - |
- January - 2020 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 150 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
No Image | |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
Pc-1/DCE submitted for approval. |
No Image |
161 (New) |
180497-Capacity Building & Skill Development of Students of Deeni Madaris |
Swabi |
30-11--1 | 30-11--1 | - | 30-11--1 | Line Deptt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2021 |
Pc-1/DCE submitted for approval. |
No Image |
Pages : 1 |