Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 2.802 | 169.642 | 0 | 100% |
97% December - 2020 |
Out of 4 bridges, 2 completed. 2 in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 2.802 | 169.642 | 0 | 100% |
97% December - 2020 |
Out of 4 bridges, 2 completed. 2 in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 8.784 | 175.624 | 0 | 100% |
100% October - 2020 |
Out of 4 bridges, all in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.042 | 8.784 | 8.784 | 8.784 | 2.8 | 168.842 | 0 | 100% |
97% September - 2020 |
Out of 4 bridges, all in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.042 | 8.784 | 8.784 | 8.784 | 2.8 | 168.842 | 0 | 100% |
97% August - 2020 |
Out of 4 bridges, all in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.042 | 8.784 | 0 | 8.784 | 0 | 166.042 | 0 | 100% |
95% July - 2020 |
Out of 4 bridges, all in progress (Agharily, Arif |
No Image |
1) Agherlay bridge
2) Arif Kala | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 3.85 | 170.69 | 0 | 100% |
98% March - 2021 |
Out of 4 bridges, 2 completed. 2 in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 3.85 | 170.69 | 0 | 100% |
98% February - 2021 |
Out of 4 bridges, 2 completed. 2 in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 3.85 | 170.69 | 0 | 100% |
98% January - 2021 |
Out of 4 bridges, 2 completed. 2 in progress.
Completion June 2021. |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 8.784 | 175.624 | 0 | 100% |
100% May - 2021 |
Out of 4 bridges, 2 completed. 2 in progress.
Cannot be completed revised PC-I submitted to P&D Departt: |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||
1609 (OG) |
140989-F/S, Design and Construction of 4 Nos. of RCC Bridges a) Aghiraly and Arif b) Darangal Khwar c) Markhanai Maidan, Dir Lower. |
Dir Lower HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 174.826 | 166.84 | 8.784 | 8.784 | 8.784 | 8.784 | 175.624 | 0 | 100% |
100% April - 2021 |
Out of 4 bridges, 2 completed. 2 in progress.
Cannot be completed revised PC-I submitted to P&D Departt: |
No Image |
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge | |||||||||||||||||||