Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 50 37.5 354.456 843.614 30% 29%
December - 2020
Length 43 Km ) (7 units) - 14 Km B/T completed. & remaining E/Work S/Work, WBM, in progress. Revised DCE submitted.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 50 37.5 354.456 843.614 30% 29%
December - 2020
Length 43 Km ) (7 units) - 14 Km B/T completed. & remaining E/Work S/Work, WBM, in progress. Revised DCE submitted.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 37.5 12.5 329.456 843.614 30% 27%
October - 2020
Length 43 Km ) (7 units) - 14 Km B/T completed. & remaining E/Work S/Work, WBM, in progress. Revised DCE submitted.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 12.5 12.5 329.456 843.614 30% 27%
September - 2020
Length 43 Km ) (7 units) - 14 Km B/T completed. & remaining E/Work S/Work, WBM, in progress. Revised DCE submitted.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 12.5 12.5 329.456 843.614 30% 27%
August - 2020
Length 43 Km ) (7 units) - (b) Work in progress
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 0 12.5 0 316.956 843.614 30% 26%
July - 2020
Length 43 Km ) (7 units) - (b) Work in progress in
No Image
1) Mian Kalay to Kambat
2) Link
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 50 50 366.956 843.614 30% 30%
March - 2021
Completed
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 50 50 366.956 843.614 30% 30%
February - 2021
Completed
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 50 50 50 366.956 843.614 30% 30%
January - 2021
Length 43 Km ) (7 units) - 14 Km B/T completed. & remaining E/Work S/Work, WBM, in progress. Revised DCE submitted.
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 60 60 54.573 371.529 843.614 30% 31%
May - 2021
07 Units 03 Units Completed 04 Units in progress Total 13/18 KM completed Demand Rs: 15 M
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
1606
(OG)
140830-F/S, Design & Construction of BT roads a) Mian Kalay to Kambat, b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir (Lower).
Dir Lower
HW
30-11--1 30-11--1 - 30-11--1 - 1210.57 316.956 50 60 60 54.573 371.529 843.614 30% 31%
April - 2021
07 Units 03 Units Completed 04 Units in progress Total 13/18 KM completed Demand Rs: 15 M
No Image
1) Mian Kalay to Kambat
2) Link road Ghwara Banda
3) Link road Gawardesh
4) Link road Janpassa
5) Link road Pratta
6) Link road Nawo Koto
7) Link road Hisarak
Pages : 1