Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 10 10 0 0 0 100% -
December - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Completion : June-2021.
No Image
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 10 10 0 0 0 100% -
December - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Completion : June-2021.
No Image
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 20 15 0 0 0 100% -
October - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Completion : June-2021.
No Image
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 20 10 0 0 0 100% -
September - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Completion : June-2021.
No Image
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 20 10 0 0 0 100% -
August - 2020
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. Completion : June-2021.
No Image
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 0 0 0 0 0 100% -
July - 2020
PC-II approved for Rs.8 m. Survery for Studying Fe
No Image
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 1.6 1.6 0 0 0 100% -
May - 2021
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Dce for Rs. 700 M under preparation. Cannot be complted as the construction phase will be included in this ADP
No Image
FS and Design of road from Odigram to Guligram, Swat
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 1.6 1.6 0 0 0 100% -
April - 2021
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Dce for Rs. 700 M under preparation. Cannot be complted as the construction phase will be included in this ADP
No Image
FS and Design of road from Odigram to Guligram, Swat
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 1.6 1.6 0 0 0 100% -
March - 2021
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Dce for Rs. 700 M under preparation. Will be completed by June 2021.
No Image
FS and Design of road from Odigram to Guligram, Swat
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 1.6 1.6 0 0 0 100% -
February - 2021
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Dce for Rs. 700 M under preparation. Will be completed by June 2021.
No Image
FS and Design of road from Odigram to Guligram, Swat
1604
(OG)
190574-FS and Design of road from Odigram to Guligram, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 8 0 20 1.6 1.6 0 0 0 100% -
January - 2021
PC-II approved for Rs.8 m. Survery for Studying Feasibility in progress. EIA report sent to Director General EPA Peshawar. Dce for Rs. 700 M under preparation. Will be completed by June 2021.
No Image
FS and Design of road from Odigram to Guligram, Swat