Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 472.767 100 100 100 75 547.767 277.334 67% 64%
December - 2020
03- Packages = 21 Units Length 38 out of 55 km completed.
No Image
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 472.767 100 100 100 75 547.767 277.334 67% 64%
December - 2020
03- Packages = 21 Units Length 38 out of 55 km completed.
No Image
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 472.767 100 100 75 73.524 546.291 277.334 67% 64%
October - 2020
03- Packages = 21 Units Completed =7 Units Package-1, Package-2, Package-3, work in progress on all packages.
No Image
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 472.767 100 100 50 25 497.767 277.334 67% 59%
September - 2020
Package-1, Package-2, Package-3, work in progress on all packages.
No Image
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 472.767 100 100 25 0 472.767 277.334 67% 56%
August - 2020
Package-1, Package-2, Package-3, work in progress on all packages.
No Image
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 472.767 100 0 0 0 472.767 277.334 67% 56%
July - 2020
Package-1, Package-2 - Work in progress. . Package
No Image
1) Construction/BT of Beryum to Nazar Abad ro
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 511.517 100 130 130 130 641.517 238.584 72% 75%
May - 2021
03- Packages = 21 Units Length 38 out of 55 km completed.
No Image
Part (A) Old Work
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
Part (B) New Work
1. Nasrat Khwar to Tarkanai Road 3 KM Package I
2. Nasrat Khwat to Tarkanai Road 2.4 KM Package II
3. Shalhand to Taran Khwar 3.5 KM
4. Taran to Drad us Stand Road 1.50 KM
5. Serai Chowk Dando Road 2.8 KM Package I
6. Serai Chowk Dando Road Package II
7. Kandaw Sekari Road 3 KM
8. Ashar Banr Road 1 KM
 
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 511.517 100 130 130 130 641.517 238.584 72% 75%
April - 2021
03- Packages = 21 Units Length 38 out of 55 km completed.
No Image
Part (A) Old Work
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
Part (B) New Work
1. Nasrat Khwar to Tarkanai Road 3 KM Package I
2. Nasrat Khwat to Tarkanai Road 2.4 KM Package II
3. Shalhand to Taran Khwar 3.5 KM
4. Taran to Drad us Stand Road 1.50 KM
5. Serai Chowk Dando Road 2.8 KM Package I
6. Serai Chowk Dando Road Package II
7. Kandaw Sekari Road 3 KM
8. Ashar Banr Road 1 KM
 
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 511.517 100 130 130 130 641.517 238.584 72% 75%
March - 2021
03- Packages = 21 Units Length 38 out of 55 km completed.
No Image
Part (A) Old Work
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
Part (B) New Work
1. Nasrat Khwar to Tarkanai Road 3 KM Package I
2. Nasrat Khwat to Tarkanai Road 2.4 KM Package II
3. Shalhand to Taran Khwar 3.5 KM
4. Taran to Drad us Stand Road 1.50 KM
5. Serai Chowk Dando Road 2.8 KM Package I
6. Serai Chowk Dando Road Package II
7. Kandaw Sekari Road 3 KM
8. Ashar Banr Road 1 KM
 
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 511.517 100 130 130 130 641.517 238.584 72% 75%
February - 2021
03- Packages = 21 Units Length 38 out of 55 km completed.
No Image
Part (A) Old Work
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
Part (B) New Work
1. Nasrat Khwar to Tarkanai Road 3 KM Package I
2. Nasrat Khwat to Tarkanai Road 2.4 KM Package II
3. Shalhand to Taran Khwar 3.5 KM
4. Taran to Drad us Stand Road 1.50 KM
5. Serai Chowk Dando Road 2.8 KM Package I
6. Serai Chowk Dando Road Package II
7. Kandaw Sekari Road 3 KM
8. Ashar Banr Road 1 KM
 
1598
(OG)
170669-Const of rd: Baryam, Nazrabad,Airport-Mamdhera,Gora-Tangai Shah,Totanu Bandai,Tangai Chena,Sigram,Mahak-Narngpura,Venai-Ochrai & Sijban-Sperdr,Reconst of rd Kalakaly-Nasrat Chk,Giga Shawr Gat-Landysr,Nasrtkhwr-Tarkani,Shalhand-Tarnkhwr,...Kndaw-Ska
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 850.101 472.767 100 100 100 100 572.767 277.334 67% 67%
January - 2021
03- Packages = 21 Units Length 38 out of 55 km completed.
No Image
Part (A) Old Work
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
Part (B) New Work
1. Nasrat Khwar to Tarkanai Road 3 KM Package I
2. Nasrat Khwat to Tarkanai Road 2.4 KM Package II
3. Shalhand to Taran Khwar 3.5 KM
4. Taran to Drad us Stand Road 1.50 KM
5. Serai Chowk Dando Road 2.8 KM Package I
6. Serai Chowk Dando Road Package II
7. Kandaw Sekari Road 3 KM
8. Ashar Banr Road 1 KM
 
Pages : 1