Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 50 50 1.033 34.854 205.52 29% 12%
December - 2020
Earth work, Sub Base,S/S work in progress. Stay order vacated. TS submitted to CE
No Image
PK-80, 81 Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 50 50 1.033 34.854 205.52 29% 12%
December - 2020
Earth work, Sub Base,S/S work in progress. Stay order vacated. TS submitted to CE
No Image
PK-80, 81 Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 50 37.5 1.033 34.854 205.52 29% 12%
October - 2020
Earth work, Sub Base,S/S work in progress.
No Image
PK-80, 81 Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 50 10 0 33.821 205.52 29% 12%
September - 2020
Earth work, Sub Base,S/S work in progress.
No Image
PK-80, 81 Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 50 10 0 33.821 205.52 29% 12%
August - 2020
Earth work, Sub Base,S/S work in progress.
No Image
PK-80, 81 Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 47.607 50 0 0 0 47.607 191.734 34% 16%
July - 2020
work started recently issue of aligment resoloved.
No Image
PK-80, 81 Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 45 45 45 78.821 205.52 29% 27%
May - 2021
Earth work, Sub Base,S/S work in progress. Stay order vacated.
No Image
PK-80, 81  Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 45 45 45 78.821 205.52 29% 27%
April - 2021
Earth work, Sub Base,S/S work in progress. Stay order vacated.
No Image
PK-80, 81  Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 45 45 44.81 78.631 205.52 29% 27%
March - 2021
Earth work, Sub Base,S/S work in progress. Stay order vacated.
No Image
PK-80, 81  Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 45 45 44.81 78.631 205.52 29% 27%
February - 2021
Earth work, Sub Base,S/S work in progress. Stay order vacated.
No Image
PK-80, 81  Swat
1595
(OG)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 289.341 33.821 50 50 50 33.234 67.055 205.52 29% 23%
January - 2021
Earth work, Sub Base,S/S work in progress. Stay order vacated.
No Image
PK-80, 81  Swat