Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 573.748 0 50 50 50 0 0 523.748 9% -
December - 2020
20 km out of 20.750 km asphlat completed. Balance work tendering in progress. Revised TS under prep
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 573.748 0 50 50 50 0 0 523.748 9% -
December - 2020
20 km out of 20.750 km asphlat completed. Balance work tendering in progress. Revised TS under prep
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 450 0 50 50 37.5 0 0 400 11% -
October - 2020
Pack-1 (Km-1 to 7) - 7 Km black-topped, stucture work 90% completed. 2) 5.4 Km black-topped, stucture work 80% completed. 3) 4Km black-topped, stucture work 90% completed. Rvised DCE for Rs. 580 M submitted.
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 450 0 50 50 12.5 0 0 400 11% -
September - 2020
Pack-1 (Km-1 to 7) - 7 Km black-topped, stucture work 90% completed. 2) 5.4 Km black-topped, stucture work 80% completed. 3) 4Km black-topped, stucture work 90% completed. Rvised DCE for Rs. 580 M submitted.
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 450 0 50 50 12.5 0 0 400 11% -
August - 2020
Pack-1 (Km-1 to 7) - 7 Km black-topped, stucture work 90% completed. 2) 5.4 Km black-topped, stucture work 80% completed. 3) 4Km black-topped, stucture work 90% completed.
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 450 364.07 50 0 0 0 364.07 35.93 92% 81%
July - 2020
Pack-1 (Km-1 to 7) - 7 Km black-topped, stucture w
No Image
1) Package-1 (Km-1 to 7)
2) Pac
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 573.748 0 50 40 40 40 40 523.748 9% 7%
May - 2021
20 km out of 20.750 km asphlat completed. Balance work (structure Wrok) tendering in progress. Stay Granted by the lower courts on Pacakge -III (7km)
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 573.748 0 50 40 40 40 40 523.748 9% 7%
April - 2021
20 km out of 20.750 km asphlat completed. Balance work (structure Wrok) tendering in progress. Stay Granted by the lower courts on Pacakge -III (7km)
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 573.748 0 50 45 45 32 32 523.748 9% 6%
March - 2021
20 km out of 20.750 km asphlat completed. Balance work (structure Wrok) tendering in progress. Stay Granted by the lower courts on Pacakge -III (7km)
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 573.748 0 50 45 45 32 32 523.748 9% 6%
February - 2021
20 km out of 20.750 km asphlat completed. Balance work (structure Wrok) tendering in progress. Stay Granted by the lower courts on Pacakge -III (7km)
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)
1591
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 573.748 0 50 50 45 11.325 11.325 523.748 9% 2%
January - 2021
20 km out of 20.750 km asphlat completed. Balance work (structure Wrok) tendering in progress. Stay Granted by the lower courts on Pacakge -III (7km)
No Image
1) Package-1 (Km-1 to 7)
2) Package-2 (Km-8 to 14)
3) Package-3 (Km-15 to 20.75)