Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 24.442 | 3.828 | 401.733 | 6.813 | 98% |
94% December - 2020 |
Bridge-completed.
Road work on right side in progress.
Decision : To be complted financially by 31st December 2020 |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 24.442 | 3.828 | 401.733 | 6.813 | 98% |
94% December - 2020 |
Bridge-completed.
Road work on right side in progress.
Decision : To be complted financially by 31st December 2020 |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 18.331 | 3.828 | 401.733 | 6.813 | 98% |
94% October - 2020 |
Bridge-completed.
Road work on right side in progress. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 6 | 0 | 397.905 | 6.813 | 98% |
93% September - 2020 |
Bridge-completed.
Road work on right side in progress. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 6 | 0 | 397.905 | 6.813 | 98% |
93% August - 2020 |
Bridge-completed.
Road work on right side in progress.
P-II: Demand 26.9 M |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 0 | 6 | 0 | 397.905 | 6.813 | 98% |
93% July - 2020 |
Bridge-completed.
Road work on right side in pro |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 | |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 24.442 | 3.828 | 401.733 | 6.813 | 98% |
94% May - 2021 |
Bridge-completed.
Road work on right side in progress. |
No Image |
RCC Bridge Length: 408 Meter
Spans 17
Spans length 24 Meter C/C
Width 8.9 Meter
Carriageway 7.3 Meter
Right Side approach 400 Meter
Left side approach 1750 Meter
| |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 24.442 | 3.828 | 401.733 | 6.813 | 98% |
94% April - 2021 |
Bridge-completed.
Road work on right side in progress. |
No Image |
RCC Bridge Length: 408 Meter
Spans 17
Spans length 24 Meter C/C
Width 8.9 Meter
Carriageway 7.3 Meter
Right Side approach 400 Meter
Left side approach 1750 Meter
| |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 24.442 | 3.828 | 401.733 | 6.813 | 98% |
94% March - 2021 |
Bridge-completed.
Road work on right side in progress.
Decision : To be complted financially by 31st December 2020 |
No Image |
RCC Bridge Length: 408 Meter
Spans 17
Spans length 24 Meter C/C
Width 8.9 Meter
Carriageway 7.3 Meter
Right Side approach 400 Meter
Left side approach 1750 Meter
| |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 24.442 | 3.828 | 401.733 | 6.813 | 98% |
94% February - 2021 |
Bridge-completed.
Road work on right side in progress.
Decision : To be complted financially by 31st December 2020 |
No Image |
RCC Bridge Length: 408 Meter
Spans 17
Spans length 24 Meter C/C
Width 8.9 Meter
Carriageway 7.3 Meter
Right Side approach 400 Meter
Left side approach 1750 Meter
| |||||||||||||||||||
1569 (OG) |
60323-Construction of RCC Bridge on River Swat along with approach road at Thana-Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 397.905 | 24.442 | 24.442 | 24.442 | 3.828 | 401.733 | 6.813 | 98% |
94% January - 2021 |
Bridge-completed.
Road work on right side in progress.
Decision : To be complted financially by 31st December 2020 |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
Pages : 1 |