Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 0 | 27.053 | 3.547 | 89% |
83% December - 2020 |
Bridge (30 mtr 2 span) - girders, transum, abutment, Stressing of Girders, Deck Slab, Railing completed & approaches in progress.
Completion : June-2021. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 0 | 27.053 | 3.547 | 89% |
83% December - 2020 |
Bridge (30 mtr 2 span) - girders, transum, abutment, Stressing of Girders, Deck Slab, Railing completed & approaches in progress.
Completion : June-2021. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 0 | 27.053 | 3.547 | 89% |
83% October - 2020 |
Bridge (30 mtr 2 span) - girders, transum, abutment, Stressing of Girders, Deck Slab, Railing completed & approaches in progress.
Completion : June-2021. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 0 | 27.053 | 3.547 | 89% |
83% September - 2020 |
Bridge (30 mtr 2 span) - girders, transum, abutment, Stressing of Girders, Deck Slab, Railing completed & approaches in progress.
Completion : June-2021. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 0 | 27.053 | 3.547 | 89% |
83% August - 2020 |
Bridge (30 mtr 2 span) - girders, transum, abutment,Stressing of Girders,Deck Slab, Railing completed & approaches in progress.
Completion : June-2021. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 30.601 | 1.93 | 0 | 1.93 | 0 | 30.601 | 0 | 100% |
94% July - 2020 |
Bridge (30 mtr 2 span) - girders, transum, abutmen |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 1.93 | 28.983 | 3.547 | 89% |
89% May - 2021 |
Bridge Completed
Approches in progress |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 1.93 | 28.983 | 3.547 | 89% |
89% April - 2021 |
Bridge Completed
Approches in progress |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 1.6 | 28.653 | 3.547 | 89% |
88% March - 2021 |
Bridge Completed
Approches in progress |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 1.6 | 28.653 | 3.547 | 89% |
88% February - 2021 |
Bridge Completed
Approches in progress |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
1556 (OG) |
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjpir Baba, Mardan |
Mardan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 32.53 | 27.053 | 1.93 | 1.93 | 1.93 | 0 | 27.053 | 3.547 | 89% |
83% January - 2021 |
Bridge (30 mtr 2 span) - girders, transum, abutment, Stressing of Girders, Deck Slab, Railing completed & approaches in progress.
Completion : June-2021. |
No Image |
Bridge shifted to Lar Jabba PK-25, Mardan (2 span 30 mtr each) | |||||||||||||||||||
Pages : 1 |