Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 160.184 141.961 29.2 29.2 29.2 0 141.961 0 100% 89%
December - 2020
Completed - Physically & financially.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km
3) Rehabilitation of Gar Aka Khel Road 1 Km
4) Rehabilitation of Zaida Bypass Road 3.60 Km
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 160.184 141.961 29.2 29.2 29.2 0 141.961 0 100% 89%
December - 2020
Completed - Physically & financially.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km
3) Rehabilitation of Gar Aka Khel Road 1 Km
4) Rehabilitation of Zaida Bypass Road 3.60 Km
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 163.7 141.961 29.2 29.2 14.6 0 141.961 0 100% 87%
October - 2020
Completed - Physically & financially.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km
3) Rehabilitation of Gar Aka Khel Road 1 Km
4) Rehabilitation of Zaida Bypass Road 3.60 Km
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 163.7 141.961 29.2 29.2 14 0 141.961 0 100% 87%
September - 2020
Completed - Physically & financially.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km
3) Rehabilitation of Gar Aka Khel Road 1 Km
4) Rehabilitation of Zaida Bypass Road 3.60 Km
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 163.7 141.961 29.2 29.2 14 0 141.961 0 100% 87%
August - 2020
05- Units Length 10 Km - earth work, sub base, base course in progress. Completion : June 2021.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km
3) Rehabilitation of Gar Aka Khel Road 1 Km
4) Rehabilitation of Zaida Bypass Road 3.60 Km
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 163.7 134.5 29.2 0 14 0 134.5 0 100% 82%
July - 2020
Length 3.2 Km - earth work, sub base, base course
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 160.184 141.961 29.2 14.6 14.6 14.404 156.365 0 100% 98%
March - 2021
Completed - Physically & financially.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km .?.?.(TS 9.030)
3) Rehabilitation of Gar Aka Khel Road 1 Km .?.?.(TS 13.667)
4) Rehabilitation of Zaida Bypass Road 3.60 Km .?.?.(TS 27.332)
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km .?.?.(TS 77.540)
6) Jhanda Pabani Road
7) Hund Lar (Drain)
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 160.184 141.961 29.2 14.6 14.6 10 151.961 0 100% 95%
February - 2021
Completed - Physically & financially.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km .?.?.(TS 9.030)
3) Rehabilitation of Gar Aka Khel Road 1 Km .?.?.(TS 13.667)
4) Rehabilitation of Zaida Bypass Road 3.60 Km .?.?.(TS 27.332)
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km .?.?.(TS 77.540)
6) Jhanda Pabani Road
7) Hund Lar (Drain)
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 160.184 141.961 29.2 14.6 14.6 10 151.961 0 100% 95%
January - 2021
Completed - Physically & financially.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km
3) Rehabilitation of Gar Aka Khel Road 1 Km
4) Rehabilitation of Zaida Bypass Road 3.60 Km
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
HW
30-11--1 30-11--1 - 30-11--1 - 160.184 141.961 29.2 25 25 20.5 162.461 0 100% 100%
May - 2021
Completed - Physically & financially. Can be complted provided balance Rs. 4.21 m given
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km .?.?.(TS 9.030)
3) Rehabilitation of Gar Aka Khel Road 1 Km .?.?.(TS 13.667)
4) Rehabilitation of Zaida Bypass Road 3.60 Km .?.?.(TS 27.332)
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km .?.?.(TS 77.540)
6) Jhanda Pabani Road
7) Hund Lar (Drain)
1547
(OG)
170582-Construction of 10 Km Road in, District Swabi.
Swabi
HW
30-11--1 30-11--1 - 30-11--1 - 160.184 141.961 29.2 25 25 20.5 162.461 0 100% 100%
April - 2021
Completed - Physically & financially. Can be complted provided balance Rs. 4.21 m given
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km .?.?.(TS 9.030)
3) Rehabilitation of Gar Aka Khel Road 1 Km .?.?.(TS 13.667)
4) Rehabilitation of Zaida Bypass Road 3.60 Km .?.?.(TS 27.332)
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km .?.?.(TS 77.540)
6) Jhanda Pabani Road
7) Hund Lar (Drain)
Pages : 1