Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 0 50 50 50 50 50 102.378 33% 33%
December - 2020
(Length = 18.135Km) (PCC streeet pavt= 690 Mtr) Work in progress.(PK -63) Demand Rs: 25 M
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 0 50 50 50 50 50 102.378 33% 33%
December - 2020
(Length = 18.135Km) (PCC streeet pavt= 690 Mtr) Work in progress.(PK -63) Demand Rs: 25 M
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 0 50 50 25 8 8 102.378 33% 5%
October - 2020
(Length = 18.135Km) (PCC streeet pavt= 690 Mtr) Work in progress.(PK -63)
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 0 50 50 8 8 8 102.378 33% 5%
September - 2020
(Length = 18.135Km) (PCC streeet pavt= 690 Mtr) Work in progress.(PK -63)
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 0 50 50 8 8 8 102.378 33% 5%
August - 2020
Work in progress.(PK -63)
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 0 50 0 8 0 0 102.378 33% -
July - 2020
Work order issued (PK -63)
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 50 50 50 50 50 100 52.378 66% 66%
May - 2021
(Length = 18.135Km) work order issued work started
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 50 50 50 50 50 100 52.378 66% 66%
April - 2021
(Length = 18.135Km) work order issued work started
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 50 50 50 50 50 100 52.378 66% 66%
March - 2021
(Length = 18.135Km) work order issued work started
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 50 50 50 50 50 100 52.378 66% 66%
February - 2021
(Length = 18.135Km) work order issued work started
No Image
1534
(OG)
190587-Construction of roads in District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 152.378 0 50 50 50 50 50 102.378 33% 33%
January - 2021
(Length = 18.135Km) (PCC streeet pavt= 690 Mtr) Work in progress.(PK -63) Demand Rs: 25 M
No Image
Pages : 1