Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 100 25 25 25 12.5 112.5 25 83% 75%
December - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 100 25 25 25 12.5 112.5 25 83% 75%
December - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 100 25 25 12.5 6.25 106.25 25 83% 71%
October - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 100 25 25 6.25 6.25 106.25 25 83% 71%
September - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 100 25 25 6.25 3.903 103.903 25 83% 69%
August - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 100 25 0 6.25 0 100 25 83% 67%
July - 2020
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 125 25 25 25 25 150 0 100% 100%
May - 2021
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 125 25 25 25 25 150 0 100% 100%
April - 2021
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 125 25 25 25 25 150 0 100% 100%
March - 2021
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 125 25 25 25 25 150 0 100% 100%
February - 2021
7 Km - 7 km asphalt completed.
No Image
Nowshera
1531
(OG)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 100 25 25 25 25 125 25 83% 83%
January - 2021
7 Km - 7 km asphalt completed.
No Image
Nowshera