Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 348.025 | 30 | 30 | 30 | 15 | 363.025 | 71.879 | 84% |
81% December - 2020 |
18 Km (original scope) - completed. Revised scope - in progress.
Demand Rs: 15 M |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 348.025 | 30 | 30 | 30 | 15 | 363.025 | 71.879 | 84% |
81% December - 2020 |
18 Km (original scope) - completed. Revised scope - in progress.
Demand Rs: 15 M |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 348.025 | 30 | 30 | 15 | 7.5 | 355.525 | 71.879 | 84% |
79% October - 2020 |
18 Km (original scope) - completed. Revised scope - in progress. |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 348.025 | 30 | 30 | 7.5 | 7.5 | 355.525 | 71.879 | 84% |
79% September - 2020 |
18 Km (original scope) - completed. Revised scope - in progress. |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 348.025 | 30 | 30 | 7.5 | 7.5 | 355.525 | 71.879 | 84% |
79% August - 2020 |
18 Km (original scope) - completed. Revised scope - in progress. |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 348.025 | 30 | 0 | 7.5 | 0 | 348.025 | 71.879 | 84% |
77% July - 2020 |
18 Km (original scope) - completed. Revised scope - in progress. |
No Image |
Package-1 - UC Dheri Katti Khel
| |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 366.178 | 30 | 22.5 | 22.5 | 20.07 | 386.248 | 53.726 | 88% |
86% May - 2021 |
18 Km (original scope) - completed. Revised scope - in progress. |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 366.178 | 30 | 22.5 | 22.5 | 20.072 | 386.25 | 53.726 | 88% |
86% April - 2021 |
18 Km (original scope) - completed. Revised scope - in progress. |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 366.178 | 30 | 22.5 | 22.5 | 18.153 | 384.331 | 53.726 | 88% |
85% March - 2021 |
18 Km (original scope) - completed. Revised scope - in progress.
Demand Rs: 15 M |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 366.178 | 30 | 22.5 | 22.5 | 18.153 | 384.331 | 53.726 | 88% |
85% February - 2021 |
18 Km (original scope) - completed. Revised scope - in progress.
Demand Rs: 15 M |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
1530 (OG) |
151074-Construction/ Pavement of roads /streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 449.904 | 348.025 | 30 | 22.5 | 22.5 | 15 | 363.025 | 71.879 | 84% |
81% January - 2021 |
18 Km (original scope) - completed. Revised scope - in progress.
Demand Rs: 15 M |
No Image |
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad | |||||||||||||||||||
Pages : 1 |