Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 359.68 40.219 40.219 40.2195 20.11 379.79 300.101 57% 54%
December - 2020
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 359.68 40.219 40.219 40.2195 20.11 379.79 300.101 57% 54%
December - 2020
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 359.68 40.219 40.219 20.1095 0 359.68 300.101 57% 51%
October - 2020
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 359.68 40.219 40.219 15 0 359.68 300.101 57% 51%
September - 2020
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 359.68 40.219 40.219 15 0 359.68 300.101 57% 51%
August - 2020
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 399.899 359.68 40.219 0 15 0 359.68 0 100% 90%
July - 2020
Length 8.5 Km - completed. Revised scope - in prog
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 379.79 40.219 31.366 31.366 31.365 411.155 279.991 60% 59%
May - 2021
Delete . Drop from ADP
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 379.79 40.219 31.336 31.336 31.365 411.155 279.991 60% 59%
April - 2021
Delete . Drop from ADP
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 379.79 40.219 40.219 40.2195 20.11 399.9 279.991 60% 57%
March - 2021
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 379.79 40.219 40.219 40.2195 20.11 399.9 279.991 60% 57%
February - 2021
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera
1527
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, G.T Road to Fazal Gange and Hassan Abad Risalpur G.T Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nows
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 700 359.68 40.219 40.219 40.2195 20.11 379.79 300.101 57% 54%
January - 2021
(Length 1.5Km) Hassan abad & Kandar road completed. Risalpur to Ghala Dher road Package-II in progress. Completion June-2021.
No Image
Nowshera