Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 3

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 4.393 1.713 1.713 1.713 1.373 5.766 1.258 83% 78%
December - 2020
Out of 5 units, 2 completed, 2 in progress, 1 not yet started
No Image
1) Masjid Targar Bannu City (improvement)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 4.393 1.713 1.713 1.713 1.373 5.766 1.258 83% 78%
December - 2020
Out of 5 units, 2 completed, 2 in progress, 1 not yet started
No Image
1) Masjid Targar Bannu City (improvement)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 0 0 0 0 0 0 7.364 - -
October - 2020
Out of 5 units, 2 completed, 2 in progress, 1 not yet started
No Image
1) Masjid Targar Bannu City (improvement)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 0 0 0 0 0 0 7.364 - -
September - 2020
Out of 5 units, 2 completed, 2 in progress, 1 not yet started
No Image
1) Masjid Targar Bannu City (improvement)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 0 0.56 0.56 0.56 0.56 0.56 6.804 8% 8%
August - 2020
Out of 5 units, 2 completed, 2 in progress, 1 not yet started
No Image
1) Masjid Targar Bannu City (improvement)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 0 0 0 0 0 0 7.364 - -
July - 2020
Out of 5 units, 2 completed, 2 in progress, 1
No Image
1) Masjid Targar Bannu City (improvement)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 4.393 1.713 1.713 1.713 1.712 6.105 1.258 83% 83%
May - 2021
05- Units 1. Completed 2. Completed 3. Completed 4. Work not started 5. Completed & H/O
No Image
1) Masjid Targar Bannu City (improvement) (TS 1.875)
2 Masjid Dr. Gul Jehan Shah Kotka Gul Ahmad  (TS 0.986)
3 Masjid Mufti Gohar Ali Shah (TS 0.974)
4 Masjid Sattar Mal Mandai Bannu City
5  Masjid at Titer Khel Jandu Khel Bannu (TS 2.331)
 
Scope of work:
  • Hall Electrificaiton
  • Water Supply
  • Tube well bore
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 4.393 1.713 1.713 1.713 1.712 6.105 1.258 83% 83%
April - 2021
Out of 5 units, 2 completed, 2 in progress, S, N0:4 not yet started
No Image
1) Masjid Targar Bannu City (improvement) (TS 1.875)
2 Masjid Dr. Gul Jehan Shah Kotka Gul Ahmad  (TS 0.986)
3 Masjid Mufti Gohar Ali Shah (TS 0.974)
4 Masjid Sattar Mal Mandai Bannu City
5  Masjid at Titer Khel Jandu Khel Bannu (TS 2.331)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 4.393 1.713 1.713 1.713 1.712 6.105 1.258 83% 83%
March - 2021
Out of 5 units, 2 completed, 2 in progress, S, N0:4 not yet started
No Image
1) Masjid Targar Bannu City (improvement) (TS 1.875)
2 Masjid Dr. Gul Jehan Shah Kotka Gul Ahmad  (TS 0.986)
3 Masjid Mufti Gohar Ali Shah (TS 0.974)
4 Masjid Sattar Mal Mandai Bannu City
5  Masjid at Titer Khel Jandu Khel Bannu (TS 2.331)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 4.393 1.713 1.713 1.713 1.373 5.766 1.258 83% 78%
February - 2021
Out of 5 units, 2 completed, 2 in progress, S, N0:4 not yet started
No Image
1) Masjid Targar Bannu City (improvement) (TS 1.875)
2 Masjid Dr. Gul Jehan Shah Kotka Gul Ahmad  (TS 0.986)
3 Masjid Mufti Gohar Ali Shah (TS 0.974)
4 Masjid Sattar Mal Mandai Bannu City
5  Masjid at Titer Khel Jandu Khel Bannu (TS 2.331)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 7.364 4.393 1.713 1.713 1.713 1.373 5.766 1.258 83% 78%
January - 2021
Out of 5 units, 2 completed, 2 in progress, 1 not yet started
No Image
1) Masjid Targar Bannu City (improvement)
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 18.112 4.2 4.2 4.2 4.2 22.312 0 100% 100%
December - 2020
3 units, 1- Fix of doors/window in progre
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 18.112 4.2 4.2 4.2 4.2 22.312 0 100% 100%
December - 2020
3 units, 1- Fix of doors/window in progre
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 0 4.2 4.2 4.2 0 0 17.8 19% -
October - 2020
3 units, 1- Fix of doors/window in progre
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 0 4.2 4.2 4.2 0 0 17.8 19% -
September - 2020
3 units, 1- Fix of doors/window in progre
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 0 0 0 0 0 0 22 - -
August - 2020
3 units, 1- Fix of doors/window in progre
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 0 0 0 0 0 0 22 - -
July - 2020
3 units, 1- Fix of doors/window in progre
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 18.112 8.487 8.487 8.487 4.621 22.733 0 100% 100%
May - 2021
03- Units 1. Completed 2. Finishing 3. Finishing
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba ? Rs; 5.0 M
2. Const: of jamia Masjid Baro Masjid Village Kalpani Buner ? Rs; 5.0M
3. Const: of Darul Uloom Tarjumnul Quran Rega Bunder ? Rs; 12.0 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 18.112 8.487 8.487 8.487 5.781 23.893 0 100% 100%
April - 2021
03 units all in finishing stage
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba ? Rs; 5.0 M
2. Const: of jamia Masjid Baro Masjid Village Kalpani Buner ? Rs; 5.0M
3. Const: of Darul Uloom Tarjumnul Quran Rega Bunder ? Rs; 12.0 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 18.112 8.487 8.487 8.487 4.621 22.733 0 100% 100%
March - 2021
03 units all in finishing stage
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba ? Rs; 5.0 M
2. Const: of jamia Masjid Baro Masjid Village Kalpani Buner ? Rs; 5.0M
3. Const: of Darul Uloom Tarjumnul Quran Rega Bunder ? Rs; 12.0 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 18.112 8.487 8.487 8.487 4.621 22.733 0 100% 100%
February - 2021
03 units all in finishing stage
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba ? Rs; 5.0 M
2. Const: of jamia Masjid Baro Masjid Village Kalpani Buner ? Rs; 5.0M
3. Const: of Darul Uloom Tarjumnul Quran Rega Bunder ? Rs; 12.0 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 22 18.112 8.487 8.487 8.487 4.621 22.733 0 100% 100%
January - 2021
3 units all in finishing stage
No Image
1) Madrassa Hadiq-ul-Uloom, Balokhan Pir Baba
2. Const: of jamia Masjid Baro Masjid Village Kalpani Buner
3. Const: of Darul Uloom Tarjumnul Quran Rega BUnder
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 2.588 0 0 0 0 2.588 0.912 - 74%
December - 2020
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 5.484 0 0 0 0 5.484 0.516 - 91%
December - 2020
Out of 2 Units, 2 unit Completed.
No Image
1. (improvement/extension) Jamia Masjid Haji abad Umarzai Distt: Charssadda? Rs: 2.00 M
2. Const: of Students Hostel in Jamia Ahyayul Uloom, Prang Distt: Charssadda? Rs: 4.00 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 2.588 0 0 0 0 2.588 0.912 - 74%
December - 2020
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 5.484 0 0 0 0 5.484 0.516 - 91%
December - 2020
Out of 2 Units, 2 unit Completed.
No Image
1. (improvement/extension) Jamia Masjid Haji abad Umarzai Distt: Charssadda? Rs: 2.00 M
2. Const: of Students Hostel in Jamia Ahyayul Uloom, Prang Distt: Charssadda? Rs: 4.00 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 0 0 0 0 0 0 6 - -
October - 2020
Out of 2 Units, 2 unit Completed.
No Image
1) (improvement/extension) Jamia Masjid Haji
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 0 0 0 0 0 0 3.5 - -
October - 2020
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 0 0 0 0 0 0 6 - -
September - 2020
Out of 2 Units, 2 unit Completed.
No Image
1) (improvement/extension) Jamia Masjid Haji
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 0 0 0 0 0 0 3.5 - -
September - 2020
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 0 0 0 0 0 0 6 - -
August - 2020
Out of 2 Units, 2 unit Completed.
No Image
1) (improvement/extension) Jamia Masjid Haji
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 0 0 0 0 0 0 3.5 - -
August - 2020
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 0 0 0 0 0 0 6 - -
July - 2020
Out of 2 Units, 1 unit Completed. 1 unit 90% compl
No Image
1) (improvement/extension) Jamia Masjid Haji
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 0 0 0 0 0 0 3.5 - -
July - 2020
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 2.588 0 0 0 0 2.588 0.912 - 74%
May - 2021
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 5.424 0 0 0 0 5.424 0.576 - 90%
May - 2021
02 Units 1. Completed 2. 90% Completed
No Image
1. (improvement/extension) Jamia Masjid Haji abad Umarzai Distt: Charssadda? Rs: 2.00 M
2. Const: of Students Hostel in Jamia Ahyayul Uloom, Prang Distt: Charssadda? Rs: 4.00 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 2.588 0 0 0 0 2.588 0.912 - 74%
April - 2021
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 5.484 0 0 0 0 5.484 0.516 - 91%
April - 2021
Out of 2 Units, 2 unit Completed.
No Image
1. (improvement/extension) Jamia Masjid Haji abad Umarzai Distt: Charssadda? Rs: 2.00 M
2. Const: of Students Hostel in Jamia Ahyayul Uloom, Prang Distt: Charssadda? Rs: 4.00 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 2.588 0 0 0 0 2.588 0.912 - 74%
March - 2021
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 5.484 0 0 0 0 5.484 0.516 - 91%
March - 2021
Out of 2 Units, 2 unit Completed.
No Image
1. (improvement/extension) Jamia Masjid Haji abad Umarzai Distt: Charssadda? Rs: 2.00 M
2. Const: of Students Hostel in Jamia Ahyayul Uloom, Prang Distt: Charssadda? Rs: 4.00 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 2.588 0 0 0 0 2.588 0.912 - 74%
February - 2021
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 5.484 0 0 0 0 5.484 0.516 - 91%
February - 2021
Out of 2 Units, 2 unit Completed.
No Image
1. (improvement/extension) Jamia Masjid Haji abad Umarzai Distt: Charssadda? Rs: 2.00 M
2. Const: of Students Hostel in Jamia Ahyayul Uloom, Prang Distt: Charssadda? Rs: 4.00 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 3.5 2.588 0 0 0 0 2.588 0.912 - 74%
January - 2021
Roof level.
No Image
Construction of Jamia Masjid Beha Matta PK--08
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 6 5.484 0 0 0 0 5.484 0.516 - 91%
January - 2021
Out of 2 Units, 2 unit Completed.
No Image
1. (improvement/extension) Jamia Masjid Haji abad Umarzai Distt: Charssadda? Rs: 2.00 M
2. Const: of Students Hostel in Jamia Ahyayul Uloom, Prang Distt: Charssadda? Rs: 4.00 M
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
December - 2020
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah v
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
December - 2020
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah v
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
October - 2020
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah v
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
September - 2020
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah v
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
August - 2020
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah v
152
(OG)
170619-Improvement and Construction of Masajid and Dar-ul-uloom in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 2 0 0 0 0 0 0 2 - -
July - 2020
Approved.
No Image
Madrassa Darul Uloom Tarjuman ul Quran Wa Sunnah v