Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 255.4935 30 30 30 0 255.4935 84.493 77% 69%
December - 2020
FWO Executed Bridge completed Demand Rs: 82.5 M Enhancemnet in progress. Physically completed
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 255.4935 30 30 30 0 255.4935 84.493 77% 69%
December - 2020
FWO Executed Bridge completed Demand Rs: 82.5 M Enhancemnet in progress. Physically completed
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 255.4935 30 30 30 0 255.4935 84.493 77% 69%
October - 2020
Bridge completed - Approaches in progress. Enhancemnet in progress.
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 191.483 30 30 7.5 0 191.483 148.503 60% 52%
September - 2020
Bridge completed - Approaches in progress. Enhancemnet in progress.
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 191.483 30 30 7.5 0 191.483 148.503 60% 52%
August - 2020
Bridge completed - Approaches in progress. Enhancemnet in progress.
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 191.483 30 0 7.5 0 191.483 148.503 60% 52%
July - 2020
Bridge completed - Approaches in progress.
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 350.098 30 130 130 94.604 444.702 0 100% 100%
May - 2021
80% Completed
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 350.098 30 130 130 94.604 444.702 0 100% 100%
April - 2021
80% Completed
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 350.098 30 130 130 94.604 444.702 0 100% 100%
March - 2021
80% Completed
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 350.098 30 130 130 94.604 444.702 0 100% 100%
February - 2021
80% Completed
No Image
Nowshera
1519
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt|:
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 369.986 255.4935 30 30 30 0 255.4935 84.493 77% 69%
January - 2021
FWO Executed Bridge completed Demand Rs: 82.5 M Enhancemnet in progress. Physically completed
No Image
Nowshera
Pages : 1