Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 13.339 13.339 1.767 145.742 0 100% 98%
December - 2020
Length 15 Km - Physcially & Financially Completed.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 13.339 13.339 1.767 145.742 0 100% 98%
December - 2020
Length 15 Km - Physcially & Financially Completed.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 13.339 7 0 143.975 0 100% 97%
October - 2020
Length 15 Km - 13 Km Asphalt completed. Completion June-2021.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 13.339 7 0 143.975 0 100% 97%
September - 2020
Length 15 Km - 13 Km Asphalt completed. Completion June-2021.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 13.339 7 0 143.975 0 100% 97%
August - 2020
Length 15 Km - 13 Km Asphalt completed. Completion June-2021.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 0 7 0 143.975 0 100% 97%
July - 2020
Length 15 Km - 13 Km Asphalt completed. P-II (Rs. 13 M Demand for completion of scheme.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony<
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 1.767 1.767 1.767 145.742 0 100% 98%
May - 2021
Length 15 Km - Physcially & Financially Completed.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 1.767 1.767 1.767 145.742 0 100% 98%
April - 2021
Length 15 Km - Physcially & Financially Completed.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 1.767 1.767 1.767 145.742 0 100% 98%
March - 2021
Length 15 Km - Physcially & Financially Completed.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 143.975 13.339 1.767 1.767 1.767 145.742 0 100% 98%
February - 2021
Length 15 Km - Physcially & Financially Completed.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
1491
(OG)
140949-F/S, Design and Construction/ Improvement of 15 Km Roads in, District Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 149.149 0 13.339 1.767 1.767 1.767 0 0
January - 2021
Length 15 Km - Physcially & Financially Completed.
No Image
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link
Pages : 1