Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 10 | 5 | 46.078 | 133.044 | 28% |
25% December - 2020 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 20 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 10 | 5 | 46.078 | 133.044 | 28% |
25% December - 2020 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 20 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 5 | 3 | 44.078 | 133.044 | 28% |
24% October - 2020 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 30 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 3 | 3 | 44.078 | 133.044 | 28% |
24% September - 2020 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 30 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 3 | 0 | 41.078 | 133.044 | 28% |
22% August - 2020 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 50.722 | 10 | 0 | 3 | 0 | 50.722 | 123.4 | 33% |
28% July - 2020 |
Earth work, structure in progress. |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 10 | 10 | 51.078 | 133.044 | 28% |
28% May - 2021 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 150 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 10 | 10 | 51.078 | 133.044 | 28% |
28% April - 2021 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 150 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 10 | 10 | 51.078 | 133.044 | 28% |
28% March - 2021 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 40 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 10 | 10 | 51.078 | 133.044 | 28% |
28% February - 2021 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 40 M |
No Image |
Hangu | |||||||||||||||||||
1489 (OG) |
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II) |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 184.122 | 41.078 | 10 | 10 | 10 | 10 | 51.078 | 133.044 | 28% |
28% January - 2021 |
Length 7 km - Earth work, structure 85 % in progress.
Demand Rs. 20 M |
No Image |
Hangu | |||||||||||||||||||
Pages : 1 |