Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 45 | 22.5 | 22.5 | 305 | 13% |
6% December - 2020 |
4/26 Units - Work started. |
No Image |
1. Repair & Rehab: of Bilitang to Kot .?. Rs; 436.184 M
2. Repair & Rehab: of kHARmatoo to Bhura Ghari Road.?. Rs; 15.213 M
3. Repair & Rehab: of Kot to Marchongi Road .?. Rs; 447.143 M
4. Repair & Rehab: of Sabir Abad Chowk to Kala Bagh .?. Rs; 27.553 M
5. Repair & Rehab: of Lachi Dartapi to Nadar Banda.?. Rs; 24.215 M
6. Repair & Rehab: of KDA Gate No. 3 to DHQ Hospital Road .?. Rs; 16.923 M
7. Repair & Rehab: of Charbagh Road .?. Rs; 2.905 M
8. Repair & Rehab: of Malang Abad Road .?. Rs; 1.823 M
9. Repair & Rehab: of Bypass to Malang Abad Chowk Road .?. Rs; 9.157 M
10. Repair & Rehab: of Gamkol Road .?. Rs; 3.245 M
11. Repair & Rehab: of Near Eid Gah Road via Sheri Villa Road .?. Rs; 3.801 M
12. Repair & Rehab: of Navay Kally Road to Gulraiz Banda to Jungle Khel Byass Road .?. Rs; 20.961 M
13. Repair & Rehab: of Eid Gah to Bypass Navay Kallay Chowk .?. Rs; 4.841 M
14. Repair & Rehab: of OTS to Sheri Villa Road .?. Rs; 13.895 M
15. Repair & Rehab: of Bypass to Momidhan Road .?. Rs; 1.792 M
16. Repair & Rehab: of Hafiz Abd Road .?. Rs; 3.564 M
17. Repair & Rehab: of Pehlawan Banda Road .?. Rs; 8.518 M
18. Repair & Rehab: of Branch Road Kachi .?. Rs; 5.180 M
19. Repair & Rehab: of Main Abdul Ali Check Post .?. Rs; 11.700 M
20. Repair & Rehab: of RCH Roa, Alizai Road, Khadizai Road, Bositang Road, Tora Wari Road, Speena Khawar Orad, Chishma Mitha Khan, & Dargah Road .?. Rs; 43.775 M
21. Repair & Rehab: of National Bank Road at Kachai .?. Rs; 2.503 M
22. Repair & Rehab: of Marai Branch Road .?. Rs; 4.223 M
23. Repair & Rehab: of Hassan Khel Kachi Road .?. Rs; 8.003 M
24. Repair & Rehab: of New Road PK-82 .?. Rs; 15.502 M
25. Repair & Rehab: of Dargah Road/Graveyar Road .?. Rs; 5.068 M
26. Repair & Rehab: of Khwaja Abad Road .?. Rs; 12.236 M | |||||||||||||||||||
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 45 | 22.5 | 22.5 | 305 | 13% |
6% December - 2020 |
4/26 Units - Work started. |
No Image |
1. Repair & Rehab: of Bilitang to Kot .?. Rs; 436.184 M
2. Repair & Rehab: of kHARmatoo to Bhura Ghari Road.?. Rs; 15.213 M
3. Repair & Rehab: of Kot to Marchongi Road .?. Rs; 447.143 M
4. Repair & Rehab: of Sabir Abad Chowk to Kala Bagh .?. Rs; 27.553 M
5. Repair & Rehab: of Lachi Dartapi to Nadar Banda.?. Rs; 24.215 M
6. Repair & Rehab: of KDA Gate No. 3 to DHQ Hospital Road .?. Rs; 16.923 M
7. Repair & Rehab: of Charbagh Road .?. Rs; 2.905 M
8. Repair & Rehab: of Malang Abad Road .?. Rs; 1.823 M
9. Repair & Rehab: of Bypass to Malang Abad Chowk Road .?. Rs; 9.157 M
10. Repair & Rehab: of Gamkol Road .?. Rs; 3.245 M
11. Repair & Rehab: of Near Eid Gah Road via Sheri Villa Road .?. Rs; 3.801 M
12. Repair & Rehab: of Navay Kally Road to Gulraiz Banda to Jungle Khel Byass Road .?. Rs; 20.961 M
13. Repair & Rehab: of Eid Gah to Bypass Navay Kallay Chowk .?. Rs; 4.841 M
14. Repair & Rehab: of OTS to Sheri Villa Road .?. Rs; 13.895 M
15. Repair & Rehab: of Bypass to Momidhan Road .?. Rs; 1.792 M
16. Repair & Rehab: of Hafiz Abd Road .?. Rs; 3.564 M
17. Repair & Rehab: of Pehlawan Banda Road .?. Rs; 8.518 M
18. Repair & Rehab: of Branch Road Kachi .?. Rs; 5.180 M
19. Repair & Rehab: of Main Abdul Ali Check Post .?. Rs; 11.700 M
20. Repair & Rehab: of RCH Roa, Alizai Road, Khadizai Road, Bositang Road, Tora Wari Road, Speena Khawar Orad, Chishma Mitha Khan, & Dargah Road .?. Rs; 43.775 M
21. Repair & Rehab: of National Bank Road at Kachai .?. Rs; 2.503 M
22. Repair & Rehab: of Marai Branch Road .?. Rs; 4.223 M
23. Repair & Rehab: of Hassan Khel Kachi Road .?. Rs; 8.003 M
24. Repair & Rehab: of New Road PK-82 .?. Rs; 15.502 M
25. Repair & Rehab: of Dargah Road/Graveyar Road .?. Rs; 5.068 M
26. Repair & Rehab: of Khwaja Abad Road .?. Rs; 12.236 M | |||||||||||||||||||
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 22.5 | 5.604 | 5.604 | 305 | 13% |
2% October - 2020 |
4/24 Units - Work started. |
No Image |
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 7 | 0 | 0 | 305 | 13% |
- September - 2020 |
4/24 Units - Work started. |
No Image |
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 7 | 0 | 0 | 305 | 13% |
- August - 2020 |
4/24 Units - Work started
TS : 30/9/2020. |
No Image |
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 0 | 7 | 0 | 0 | 305 | 13% |
- July - 2020 |
Work order issued. |
No Image |
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 45 | 44.999 | 44.999 | 305 | 13% |
13% March - 2021 |
4/26 Units - Work started. |
No Image |
1. Repair & Rehab: of Bilitang to Kot .?. Rs; 436.184 M
2. Repair & Rehab: of kHARmatoo to Bhura Ghari Road.?. Rs; 15.213 M
3. Repair & Rehab: of Kot to Marchongi Road .?. Rs; 447.143 M
4. Repair & Rehab: of Sabir Abad Chowk to Kala Bagh .?. Rs; 27.553 M
5. Repair & Rehab: of Lachi Dartapi to Nadar Banda.?. Rs; 24.215 M
6. Repair & Rehab: of KDA Gate No. 3 to DHQ Hospital Road .?. Rs; 16.923 M
7. Repair & Rehab: of Charbagh Road .?. Rs; 2.905 M
8. Repair & Rehab: of Malang Abad Road .?. Rs; 1.823 M
9. Repair & Rehab: of Bypass to Malang Abad Chowk Road .?. Rs; 9.157 M
10. Repair & Rehab: of Gamkol Road .?. Rs; 3.245 M
11. Repair & Rehab: of Near Eid Gah Road via Sheri Villa Road .?. Rs; 3.801 M
12. Repair & Rehab: of Navay Kally Road to Gulraiz Banda to Jungle Khel Byass Road .?. Rs; 20.961 M
13. Repair & Rehab: of Eid Gah to Bypass Navay Kallay Chowk .?. Rs; 4.841 M
14. Repair & Rehab: of OTS to Sheri Villa Road .?. Rs; 13.895 M
15. Repair & Rehab: of Bypass to Momidhan Road .?. Rs; 1.792 M
16. Repair & Rehab: of Hafiz Abd Road .?. Rs; 3.564 M
17. Repair & Rehab: of Pehlawan Banda Road .?. Rs; 8.518 M
18. Repair & Rehab: of Branch Road Kachi .?. Rs; 5.180 M
19. Repair & Rehab: of Main Abdul Ali Check Post .?. Rs; 11.700 M
20. Repair & Rehab: of RCH Roa, Alizai Road, Khadizai Road, Bositang Road, Tora Wari Road, Speena Khawar Orad, Chishma Mitha Khan, & Dargah Road .?. Rs; 43.775 M
21. Repair & Rehab: of National Bank Road at Kachai .?. Rs; 2.503 M
22. Repair & Rehab: of Marai Branch Road .?. Rs; 4.223 M
23. Repair & Rehab: of Hassan Khel Kachi Road .?. Rs; 8.003 M
24. Repair & Rehab: of New Road PK-82 .?. Rs; 15.502 M
25. Repair & Rehab: of Dargah Road/Graveyar Road .?. Rs; 5.068 M
26. Repair & Rehab: of Khwaja Abad Road .?. Rs; 12.236 M | |||||||||||||||||||
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 45 | 44.999 | 44.999 | 305 | 13% |
13% February - 2021 |
4/26 Units - Work started. |
No Image |
1. Repair & Rehab: of Bilitang to Kot .?. Rs; 436.184 M
2. Repair & Rehab: of kHARmatoo to Bhura Ghari Road.?. Rs; 15.213 M
3. Repair & Rehab: of Kot to Marchongi Road .?. Rs; 447.143 M
4. Repair & Rehab: of Sabir Abad Chowk to Kala Bagh .?. Rs; 27.553 M
5. Repair & Rehab: of Lachi Dartapi to Nadar Banda.?. Rs; 24.215 M
6. Repair & Rehab: of KDA Gate No. 3 to DHQ Hospital Road .?. Rs; 16.923 M
7. Repair & Rehab: of Charbagh Road .?. Rs; 2.905 M
8. Repair & Rehab: of Malang Abad Road .?. Rs; 1.823 M
9. Repair & Rehab: of Bypass to Malang Abad Chowk Road .?. Rs; 9.157 M
10. Repair & Rehab: of Gamkol Road .?. Rs; 3.245 M
11. Repair & Rehab: of Near Eid Gah Road via Sheri Villa Road .?. Rs; 3.801 M
12. Repair & Rehab: of Navay Kally Road to Gulraiz Banda to Jungle Khel Byass Road .?. Rs; 20.961 M
13. Repair & Rehab: of Eid Gah to Bypass Navay Kallay Chowk .?. Rs; 4.841 M
14. Repair & Rehab: of OTS to Sheri Villa Road .?. Rs; 13.895 M
15. Repair & Rehab: of Bypass to Momidhan Road .?. Rs; 1.792 M
16. Repair & Rehab: of Hafiz Abd Road .?. Rs; 3.564 M
17. Repair & Rehab: of Pehlawan Banda Road .?. Rs; 8.518 M
18. Repair & Rehab: of Branch Road Kachi .?. Rs; 5.180 M
19. Repair & Rehab: of Main Abdul Ali Check Post .?. Rs; 11.700 M
20. Repair & Rehab: of RCH Roa, Alizai Road, Khadizai Road, Bositang Road, Tora Wari Road, Speena Khawar Orad, Chishma Mitha Khan, & Dargah Road .?. Rs; 43.775 M
21. Repair & Rehab: of National Bank Road at Kachai .?. Rs; 2.503 M
22. Repair & Rehab: of Marai Branch Road .?. Rs; 4.223 M
23. Repair & Rehab: of Hassan Khel Kachi Road .?. Rs; 8.003 M
24. Repair & Rehab: of New Road PK-82 .?. Rs; 15.502 M
25. Repair & Rehab: of Dargah Road/Graveyar Road .?. Rs; 5.068 M
26. Repair & Rehab: of Khwaja Abad Road .?. Rs; 12.236 M | |||||||||||||||||||
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 45 | 44.999 | 44.999 | 305 | 13% |
13% January - 2021 |
4/26 Units - Work started. |
No Image |
1. Repair & Rehab: of Bilitang to Kot .?. Rs; 436.184 M
2. Repair & Rehab: of kHARmatoo to Bhura Ghari Road.?. Rs; 15.213 M
3. Repair & Rehab: of Kot to Marchongi Road .?. Rs; 447.143 M
4. Repair & Rehab: of Sabir Abad Chowk to Kala Bagh .?. Rs; 27.553 M
5. Repair & Rehab: of Lachi Dartapi to Nadar Banda.?. Rs; 24.215 M
6. Repair & Rehab: of KDA Gate No. 3 to DHQ Hospital Road .?. Rs; 16.923 M
7. Repair & Rehab: of Charbagh Road .?. Rs; 2.905 M
8. Repair & Rehab: of Malang Abad Road .?. Rs; 1.823 M
9. Repair & Rehab: of Bypass to Malang Abad Chowk Road .?. Rs; 9.157 M
10. Repair & Rehab: of Gamkol Road .?. Rs; 3.245 M
11. Repair & Rehab: of Near Eid Gah Road via Sheri Villa Road .?. Rs; 3.801 M
12. Repair & Rehab: of Navay Kally Road to Gulraiz Banda to Jungle Khel Byass Road .?. Rs; 20.961 M
13. Repair & Rehab: of Eid Gah to Bypass Navay Kallay Chowk .?. Rs; 4.841 M
14. Repair & Rehab: of OTS to Sheri Villa Road .?. Rs; 13.895 M
15. Repair & Rehab: of Bypass to Momidhan Road .?. Rs; 1.792 M
16. Repair & Rehab: of Hafiz Abd Road .?. Rs; 3.564 M
17. Repair & Rehab: of Pehlawan Banda Road .?. Rs; 8.518 M
18. Repair & Rehab: of Branch Road Kachi .?. Rs; 5.180 M
19. Repair & Rehab: of Main Abdul Ali Check Post .?. Rs; 11.700 M
20. Repair & Rehab: of RCH Roa, Alizai Road, Khadizai Road, Bositang Road, Tora Wari Road, Speena Khawar Orad, Chishma Mitha Khan, & Dargah Road .?. Rs; 43.775 M
21. Repair & Rehab: of National Bank Road at Kachai .?. Rs; 2.503 M
22. Repair & Rehab: of Marai Branch Road .?. Rs; 4.223 M
23. Repair & Rehab: of Hassan Khel Kachi Road .?. Rs; 8.003 M
24. Repair & Rehab: of New Road PK-82 .?. Rs; 15.502 M
25. Repair & Rehab: of Dargah Road/Graveyar Road .?. Rs; 5.068 M
26. Repair & Rehab: of Khwaja Abad Road .?. Rs; 12.236 M | |||||||||||||||||||
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 45 | 45 | 45 | 305 | 13% |
13% May - 2021 |
4/26 Units - Work started.
Demand : 50 M Liability |
No Image |
1. Repair & Rehab: of Bilitang to Kot .?. Rs; 436.184 M
2. Repair & Rehab: of kHARmatoo to Bhura Ghari Road.?. Rs; 15.213 M
3. Repair & Rehab: of Kot to Marchongi Road .?. Rs; 447.143 M
4. Repair & Rehab: of Sabir Abad Chowk to Kala Bagh .?. Rs; 27.553 M
5. Repair & Rehab: of Lachi Dartapi to Nadar Banda.?. Rs; 24.215 M
6. Repair & Rehab: of KDA Gate No. 3 to DHQ Hospital Road .?. Rs; 16.923 M
7. Repair & Rehab: of Charbagh Road .?. Rs; 2.905 M
8. Repair & Rehab: of Malang Abad Road .?. Rs; 1.823 M
9. Repair & Rehab: of Bypass to Malang Abad Chowk Road .?. Rs; 9.157 M
10. Repair & Rehab: of Gamkol Road .?. Rs; 3.245 M
11. Repair & Rehab: of Near Eid Gah Road via Sheri Villa Road .?. Rs; 3.801 M
12. Repair & Rehab: of Navay Kally Road to Gulraiz Banda to Jungle Khel Byass Road .?. Rs; 20.961 M
13. Repair & Rehab: of Eid Gah to Bypass Navay Kallay Chowk .?. Rs; 4.841 M
14. Repair & Rehab: of OTS to Sheri Villa Road .?. Rs; 13.895 M
15. Repair & Rehab: of Bypass to Momidhan Road .?. Rs; 1.792 M
16. Repair & Rehab: of Hafiz Abd Road .?. Rs; 3.564 M
17. Repair & Rehab: of Pehlawan Banda Road .?. Rs; 8.518 M
18. Repair & Rehab: of Branch Road Kachi .?. Rs; 5.180 M
19. Repair & Rehab: of Main Abdul Ali Check Post .?. Rs; 11.700 M
20. Repair & Rehab: of RCH Roa, Alizai Road, Khadizai Road, Bositang Road, Tora Wari Road, Speena Khawar Orad, Chishma Mitha Khan, & Dargah Road .?. Rs; 43.775 M
21. Repair & Rehab: of National Bank Road at Kachai .?. Rs; 2.503 M
22. Repair & Rehab: of Marai Branch Road .?. Rs; 4.223 M
23. Repair & Rehab: of Hassan Khel Kachi Road .?. Rs; 8.003 M
24. Repair & Rehab: of New Road PK-82 .?. Rs; 15.502 M
25. Repair & Rehab: of Dargah Road/Graveyar Road .?. Rs; 5.068 M
26. Repair & Rehab: of Khwaja Abad Road .?. Rs; 12.236 M | |||||||||||||||||||
1487 (OG) |
190550-Construction of C&W roads in Tehsil Kohat, Gumbat and Lachi District Kohat |
Kohat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 0 | 45 | 45 | 45 | 45 | 45 | 305 | 13% |
13% April - 2021 |
4/26 Units - Work started.
Demand : 50 M Liability |
No Image |
1. Repair & Rehab: of Bilitang to Kot .?. Rs; 436.184 M
2. Repair & Rehab: of kHARmatoo to Bhura Ghari Road.?. Rs; 15.213 M
3. Repair & Rehab: of Kot to Marchongi Road .?. Rs; 447.143 M
4. Repair & Rehab: of Sabir Abad Chowk to Kala Bagh .?. Rs; 27.553 M
5. Repair & Rehab: of Lachi Dartapi to Nadar Banda.?. Rs; 24.215 M
6. Repair & Rehab: of KDA Gate No. 3 to DHQ Hospital Road .?. Rs; 16.923 M
7. Repair & Rehab: of Charbagh Road .?. Rs; 2.905 M
8. Repair & Rehab: of Malang Abad Road .?. Rs; 1.823 M
9. Repair & Rehab: of Bypass to Malang Abad Chowk Road .?. Rs; 9.157 M
10. Repair & Rehab: of Gamkol Road .?. Rs; 3.245 M
11. Repair & Rehab: of Near Eid Gah Road via Sheri Villa Road .?. Rs; 3.801 M
12. Repair & Rehab: of Navay Kally Road to Gulraiz Banda to Jungle Khel Byass Road .?. Rs; 20.961 M
13. Repair & Rehab: of Eid Gah to Bypass Navay Kallay Chowk .?. Rs; 4.841 M
14. Repair & Rehab: of OTS to Sheri Villa Road .?. Rs; 13.895 M
15. Repair & Rehab: of Bypass to Momidhan Road .?. Rs; 1.792 M
16. Repair & Rehab: of Hafiz Abd Road .?. Rs; 3.564 M
17. Repair & Rehab: of Pehlawan Banda Road .?. Rs; 8.518 M
18. Repair & Rehab: of Branch Road Kachi .?. Rs; 5.180 M
19. Repair & Rehab: of Main Abdul Ali Check Post .?. Rs; 11.700 M
20. Repair & Rehab: of RCH Roa, Alizai Road, Khadizai Road, Bositang Road, Tora Wari Road, Speena Khawar Orad, Chishma Mitha Khan, & Dargah Road .?. Rs; 43.775 M
21. Repair & Rehab: of National Bank Road at Kachai .?. Rs; 2.503 M
22. Repair & Rehab: of Marai Branch Road .?. Rs; 4.223 M
23. Repair & Rehab: of Hassan Khel Kachi Road .?. Rs; 8.003 M
24. Repair & Rehab: of New Road PK-82 .?. Rs; 15.502 M
25. Repair & Rehab: of Dargah Road/Graveyar Road .?. Rs; 5.068 M
26. Repair & Rehab: of Khwaja Abad Road .?. Rs; 12.236 M | |||||||||||||||||||