Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 30 | 15 | 262.637 | 28.589 | 91% |
86% December - 2020 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand : Balance allocation |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 30 | 15 | 262.637 | 28.589 | 91% |
86% December - 2020 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand : Balance allocation |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 15 | 7.5 | 255.137 | 28.589 | 91% |
83% October - 2020 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand Rs. 7.5 M |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 7.5 | 7.5 | 255.137 | 28.589 | 91% |
83% September - 2020 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand Rs. 7.5 M |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 7.5 | 6.6 | 254.237 | 28.589 | 91% |
83% August - 2020 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
TS : 30/9/2020. |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 0 | 7.5 | 0 | 247.637 | 28.589 | 91% |
81% July - 2020 |
Bridge at Tarali - piles 64/80 completed, 1 pile c |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 30 | 22.06 | 269.697 | 28.589 | 91% |
88% March - 2021 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand : Balance allocation |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 30 | 22.06 | 269.697 | 28.589 | 91% |
88% February - 2021 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand : Balance allocation |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 30 | 19.008 | 266.645 | 28.589 | 91% |
87% January - 2021 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand : Balance allocation |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 30 | 30 | 277.637 | 28.589 | 91% |
91% May - 2021 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand : 20 M Liability |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||
1486 (OG) |
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha khel road Rehman abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in UCs, Sodhal, Lachi rural, Mandori District Kohat |
Kohat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 306.226 | 247.637 | 30 | 30 | 30 | 30 | 277.637 | 28.589 | 91% |
91% April - 2021 |
Bridge at Tarali - piles 64/80 completed,
Package-II completed.
Package -I approaches in progress.
Demand : 20 M Liability |
No Image |
1) Banda Fateh Khel, Darmalak Road (2 Km)
2) Darmalak to Ghorzandi Road (0.5 Km)
3) Darsha Khel to Rehman Abad Paka (1 Km)
4) Karapa to Shakardar Road and Bridge Tralay (1 Km and 2600 rft)
5) UC Sudal, Lachi and Mandori (2 Km) | |||||||||||||||||||