Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 10 4.113 16.579 84.953 28% 14%
December - 2020
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 25 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 10 4.113 16.579 84.953 28% 14%
December - 2020
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 25 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 10 3.333 15.799 84.953 28% 13%
October - 2020
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 25 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 3.333 0 12.466 84.953 28% 11%
September - 2020
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 25 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 3.333 0 12.466 84.953 28% 11%
August - 2020
Masonry work in progress.
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 0 3.333 0 12.466 84.953 28% 11%
July - 2020
Length 5 Km- KM 5 WBM in progress. KM 1-4 -Work
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 20 15.563 28.029 84.953 28% 24%
May - 2021
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 20 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 20 15.563 28.029 84.953 28% 24%
April - 2021
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 20 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 20 15.218 27.684 84.953 28% 24%
March - 2021
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 20 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 20 11.087 23.553 84.953 28% 20%
February - 2021
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 20 M
No Image
Karak
1484
(OG)
170567-Construction of Black Topped road from Terri to Kot Banda at Tehsil Banda Daud Shah, District Karak
Karak
30-11--1 30-11--1 - 30-11--1 - 117.419 12.466 20 20 20 10.742 23.208 84.953 28% 20%
January - 2021
5 km road - 1 km Asphlat in progress 4 km - Started Demand Rs. 25 M
No Image
Karak
Pages : 1