Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 52.582 | 23.092 | 395.84 | 0 | 100% |
100% December - 2020 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Completion June-2021.
As per TS 29 M demnded |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 52.582 | 23.092 | 395.84 | 0 | 100% |
100% December - 2020 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Completion June-2021.
As per TS 29 M demnded |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 26.291 | 4.126 | 376.874 | 0 | 100% |
97% October - 2020 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Completion June-2021. |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 25 | 4.125 | 376.873 | 0 | 100% |
97% September - 2020 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Completion June-2021. |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 25 | 4.125 | 376.873 | 0 | 100% |
97% August - 2020 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Completion June-2021. |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 0 | 25 | 0 | 372.748 | 0 | 100% |
96% July - 2020 |
Length 4.225 Km (width 40 ft) - 3.2 Km both lane B |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 52.582 | 36.516 | 409.264 | 0 | 100% |
100% May - 2021 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Demand Rs: 26 M |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 52.582 | 36.516 | 409.264 | 0 | 100% |
100% April - 2021 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Demand Rs: 26 M |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 52.582 | 23.777 | 396.525 | 0 | 100% |
100% March - 2021 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Demand Rs: 26 M |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 52.582 | 21.092 | 393.84 | 0 | 100% |
100% February - 2021 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Demand Rs: 26 M |
No Image |
Karak | |||||||||||||||||||
1481 (OG) |
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km) |
Karak |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 390.218 | 372.748 | 52.582 | 52.582 | 52.582 | 23.092 | 395.84 | 0 | 100% |
100% January - 2021 |
(Length 4.225 Km)
E/W,S/B,WBM completed Asphalt in progress.
Completion June-2021. |
No Image |
Karak | |||||||||||||||||||
Pages : 1 |