Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 10 5 15 100.75 17% 12%
December - 2020
01- Units Work started.
No Image
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 10 5 15 100.75 17% 12%
December - 2020
01- Units Work started.
No Image
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 5 2 12 100.75 17% 10%
October - 2020
Work started.
No Image
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 2 2 12 100.75 17% 10%
September - 2020
Work started.
No Image
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 2 0 10 100.75 17% 8%
August - 2020
Work started.
No Image
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 0 2 0 10 100.75 17% 8%
July - 2020
Work started
No Image
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 10 10 20 100.75 17% 17%
March - 2021
01- Units Work started.
No Image
Bannu
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 10 10 20 100.75 17% 17%
February - 2021
01- Units Work started.
No Image
Bannu
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 10 10 5 15 100.75 17% 12%
January - 2021
01- Units Work started.
No Image
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 19 19 10 20 100.75 17% 17%
May - 2021
01- Units Work started.
No Image
Bannu
1477
(OG)
170667-Construction / BT and Reconstruction of Road at Kalan Mera Khel via Barara Mera Khel to Hamedi road Hassan Khel via Khujari to Barat Ada Kakki Road, District Bannu (8.50 Km)
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 120.75 10 10 19 19 10 20 100.75 17% 17%
April - 2021
01- Units Work started.
No Image
Bannu