Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 20 9.876 60.925 78.951 47% 41%
December - 2020
Length 6 Km - 3 km completed. P-II : balance funds
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 20 9.876 60.925 78.951 47% 41%
December - 2020
Length 6 Km - 3 km completed. P-II : balance funds
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 10 4.554 55.603 78.951 47% 37%
October - 2020
Length 6 Km - earth work, sub base 80% completed.
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 5 4.354 55.403 78.951 47% 37%
September - 2020
Length 6 Km - earth work, sub base 80% completed.
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 5 5 56.049 78.951 47% 37%
August - 2020
Length 6 Km - earth work, sub base 80% completed.
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 0 5 0 51.049 78.951 47% 34%
July - 2020
Length 6 Km - earth work, sub base 80% completed.B
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 20 20 71.049 78.951 47% 47%
March - 2021
Length 6 Km - 3 km completed. P-II : balance funds
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 20 20 71.049 78.951 47% 47%
February - 2021
Length 6 Km - 3 km completed. P-II : balance funds
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 20 15.943 66.992 78.951 47% 45%
January - 2021
Length 6 Km - 3 km completed. P-II : balance funds
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
HW
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 20 20 71.049 78.951 47% 47%
May - 2021
Length 6 Km - 3 km completed. Demand Rs: 15 M
No Image
PK-76, Lakki Marwat
1466
(OG)
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
HW
30-11--1 30-11--1 - 30-11--1 - 150 51.049 20 20 20 20 71.049 78.951 47% 47%
April - 2021
Length 6 Km - 3 km completed. Demand Rs: 15 M
No Image
PK-76, Lakki Marwat
Pages : 1