Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 20 | 9.876 | 60.925 | 78.951 | 47% |
41% December - 2020 |
Length 6 Km - 3 km completed.
P-II : balance funds |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 20 | 9.876 | 60.925 | 78.951 | 47% |
41% December - 2020 |
Length 6 Km - 3 km completed.
P-II : balance funds |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 10 | 4.554 | 55.603 | 78.951 | 47% |
37% October - 2020 |
Length 6 Km - earth work, sub base 80% completed. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 5 | 4.354 | 55.403 | 78.951 | 47% |
37% September - 2020 |
Length 6 Km - earth work, sub base 80% completed. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 5 | 5 | 56.049 | 78.951 | 47% |
37% August - 2020 |
Length 6 Km - earth work, sub base 80% completed. |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 0 | 5 | 0 | 51.049 | 78.951 | 47% |
34% July - 2020 |
Length 6 Km - earth work, sub base 80% completed.B |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 20 | 20 | 71.049 | 78.951 | 47% |
47% March - 2021 |
Length 6 Km - 3 km completed.
P-II : balance funds |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 20 | 20 | 71.049 | 78.951 | 47% |
47% February - 2021 |
Length 6 Km - 3 km completed.
P-II : balance funds |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 20 | 15.943 | 66.992 | 78.951 | 47% |
45% January - 2021 |
Length 6 Km - 3 km completed.
P-II : balance funds |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 20 | 20 | 71.049 | 78.951 | 47% |
47% May - 2021 |
Length 6 Km - 3 km completed.
Demand Rs: 15 M |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||
1466 (OG) |
150797-Construction/ Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat. |
Lakki Marwat HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 51.049 | 20 | 20 | 20 | 20 | 71.049 | 78.951 | 47% |
47% April - 2021 |
Length 6 Km - 3 km completed.
Demand Rs: 15 M |
No Image |
PK-76, Lakki Marwat | |||||||||||||||||||