Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 38.53 14.06 173.653 0 100% 88%
December - 2020
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 38.53 14.06 173.653 0 100% 88%
December - 2020
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 19.265 9.881 169.474 0 100% 86%
October - 2020
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 15 9.881 169.474 0 100% 86%
September - 2020
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 15 0 159.593 0 100% 81%
August - 2020
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 0 15 0 159.593 0 100% 81%
July - 2020
Length 10.24 Km -Zafarabad portion - 2.25 Km BT co
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 38.53 22.3 181.893 0 100% 92%
May - 2021
Length 10.24 Km - completed. Compleetd - delet from Draft ADP.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 38.53 22.3 181.893 0 100% 92%
April - 2021
Length 10.24 Km - completed. Compleetd - delet from Draft ADP.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 38.53 18.149 177.742 0 100% 90%
March - 2021
Length 10.24 Km Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 38.53 18.149 177.742 0 100% 90%
February - 2021
Length 10.24 Km Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works
1459
(OG)
150780-Const/Reh: of road A)Tank Ada-Zafarabad Clny& Daraban Chungi B)Crclr rd-Muryali Mor, Shahalam Abad,Eye Hsptl rd,Chashma rd-Vill Singar,S/Yusafabad, D.I.Khan a)Crclr rd-Multan rd b)Diyal c)Banu rd-Kotli d)TB Hsptl Chk-Circ/Hous e)Drain(Kotli-Shobra
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 198.123 159.593 38.53 38.53 38.53 14.06 173.653 0 100% 88%
January - 2021
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Completion June-2021.
No Image
1) Tank Adda to Zafar Abad Colony 1.70 Km
2) Tank Adda to Daraban Chungi (Din Pur) 1.60 Km
3) Circular road to Muryali Mor (Multan road) 2.25 Km
4) Shah Alam Abad/Eye Hospital road 1.09 Km
5) Chashma road to village Singar 0.60 Km
6) Sheikh Yousaf (Grid Road) 3 Km
7) Road from Circular road to Multan road (old Sabzi Mandi front) - additional works
8) Rehabilitation of Diyal road balance length - additional works
9) Construction of Bannu raod to Kotli road - additional works
10) TB Hospital Chowk to Circuit House road - additional works
11) Repair/construction of Drain from Kotli to Shobra Hotel - additional works