Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 178.586 | 31.057 | 31.057 | 31.0565 | 10.43 | 189.016 | 10.576 | 95% |
86% December - 2020 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Completion June-2021. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 178.586 | 31.057 | 31.057 | 31.0565 | 10.43 | 189.016 | 10.576 | 95% |
86% December - 2020 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Completion June-2021. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 189.162 | 31.057 | 31.057 | 15.5285 | 0 | 189.162 | 0 | 100% |
86% October - 2020 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Completion June-2021. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 189.162 | 31.057 | 31.057 | 12 | 0 | 189.162 | 0 | 100% |
86% September - 2020 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Completion June-2021. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 189.162 | 31.057 | 31.057 | 12 | 0 | 189.162 | 0 | 100% |
86% August - 2020 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Completion June-2021. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 189.162 | 31.057 | 0 | 12 | 0 | 189.162 | 0 | 100% |
86% July - 2020 |
Length 16 Km -Completed. (original Scope)
Revised Scope (Lora Bridge (length 120 ft, 4 span) |
No Image |
1) Construction of Bridge on Lura Nullah at D | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 178.586 | 31.057 | 31.057 | 31.0565 | 22.193 | 200.779 | 10.576 | 95% |
91% May - 2021 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued. In Progress
Cannot be completed in CFY as the revised Scope Started.
TF : Rs. 10 M |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 178.586 | 31.057 | 31.057 | 31.0565 | 22.193 | 200.779 | 10.576 | 95% |
91% April - 2021 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued. In Progress
Cannot be completed in CFY as the revised Scope Started.
TF : Rs. 10 M |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 178.586 | 31.057 | 31.057 | 31.0565 | 19.428 | 198.014 | 10.576 | 95% |
90% March - 2021 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Demand Rs: 10 M |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 178.586 | 31.057 | 31.057 | 31.0565 | 19.428 | 198.014 | 10.576 | 95% |
90% February - 2021 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Demand Rs: 10 M |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||
1458 (OG) |
140987-F/S, Design and Construction of main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi D.I. Khan i) Kirri Shamozai to Jhoke Rind (1Km), ii) Bridge on Lora Jullah Daraban City. |
D.I.Khan HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 220.219 | 178.586 | 31.057 | 31.057 | 31.0565 | 10.43 | 189.016 | 10.576 | 95% |
86% January - 2021 |
Length 16 Km -Completed. (original Scope) .
Revised Scope (Lora Bridge (length 120 ft, 4 span) - Bridge sub structure work order issued.
Completion June-2021. |
No Image |
1) Construction of Bridge on Lura Nullah at Daraban PK-67 (additionnal works)
2) Improvement and BTR from Kirri Shamozai to Jhoke Rind PK-67 1 Km (additionnal works) | |||||||||||||||||||