Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 1

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 61.292 10.464 10.464 10.464 10.464 71.756 22.053 76% 76%
December - 2020
Building Completed. Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. TS Submitted to SE. P-II: Balance Funds. Demand: 28.582 M.
No Image
1. Reconstruction of C&W Office, Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 61.292 10.464 10.464 10.464 10.464 71.756 22.053 76% 76%
December - 2020
Building Completed. Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. TS Submitted to SE. P-II: Balance Funds. Demand: 28.582 M.
No Image
1. Reconstruction of C&W Office, Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 61.292 10.464 10.464 12.696 10.454 71.746 22.053 76% 76%
October - 2020
Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. P-II: 28 M as per AA
No Image
Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 61.292 10.464 10.464 10.454 10.454 71.746 22.053 76% 76%
September - 2020
Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. P-II: 28 M as per AA
No Image
Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 61.292 10.464 10.464 10.454 10.454 71.746 22.053 76% 76%
August - 2020
Building Completed. Boundary Wall in Progress. RCC Column completed. Bore completed. P-II: 28 M as per AA
No Image
Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 61.292 10.464 0 0 0 61.292 22.053 76% 65%
July - 2020
Building Completed. Boundary Wall in Progress. RCC Column completed
No Image
Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 0 10.464 39.046 39.046 29.679 0 0
May - 2021
01-Unit M. Building Completed. Boundary Wall completed. Dev: work 95% Completed Int: Elec: Completed Bore Hole Completed Fire Fighting Completed Sewerage System Completed TS Submitted to SE. P-II: Balance Funds. Demand: 28.582 M.
No Image
1. Reconstruction of C&W Office, Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 0 10.464 14.464 14.464 14.464 0 0
April - 2021
Building Completed. Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. TS Submitted to SE. P-II: Balance Funds. Demand: 28.582 M.
No Image
1. Reconstruction of C&W Office, Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 0 10.464 14.464 14.464 14.464 0 0
March - 2021
Building Completed. Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. TS Submitted to SE. P-II: Balance Funds. Demand: 28.582 M.
No Image
1. Reconstruction of C&W Office, Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 0 10.464 14.464 14.464 14.464 0 0
February - 2021
Building Completed. Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. TS Submitted to SE. P-II: Balance Funds. Demand: 28.582 M.
No Image
1. Reconstruction of C&W Office, Kohat
1449
(OG)
170167-Reconstruction of C&W Office, Kohat
Kohat
30-11--1 30-11--1 - 30-11--1 - 93.809 61.292 10.464 10.464 10.464 10.464 71.756 22.053 76% 76%
January - 2021
Building Completed. Building Completed. Boundary Wall completed. RCC Column completed. Bore completed. TS Submitted to SE. P-II: Balance Funds. Demand: 28.582 M.
No Image
1. Reconstruction of C&W Office, Kohat
Pages : 1